Mar 22: Rs. 3909 crore greenfield pumped storage project: EPC package ahead 8The public hearing and land acquisition have been completed. 8Forest clearance stage 1 has been granted 8RFQ for the EPC package for civil and HM package is likely to be floated in Q2 2023. Rs 2074 crore greenfield hydroelectric project: RFQ coming up 8Forest clearance stage 1 has been granted. 8DPR has been approved 8RFQ for the EPC package is likely to be floated in May 2023 Rs 11054 crore greenfield pumped storage project: Civil works ahead 8EIA / EMP reports have been completed 8PMC has been selected 8RFQ for the civil works package is likely to be floated in Q2 2023. Get in touch with us for more on these project