Software update: Fertilizer projects
Feb 18: Ammonia-Urea Energy Saving Project
8Cost - Rs 250 crore
8Project Event: The feasibility studies are still ongoing, and they are likely to be completed at the end of March 2020. RFQ for the process licensor as well as LSTK contractor is likely to be released in April 2020.
Click here for more details

DAP Expansion Project
8Cost - Rs 442 crore
8Project Event: 50 % erection work has been completed, all equipment has reached the site but installation has not started yet, and is likely in March 2020. The commissioning has been delayed by two months from August to October 2020.
Click here for more details (Availble only through www.indianfertilizer.com)


**********************************