Catalytic iso-dewaxing and catalytic dewaxing units: RFQs ahead
Feb 19: 8Cost Rs 2300 crore (for both) 8The two projects are now progressing independently. 8The project is envisaged to be implemented in hybrid mode: Inside Battery Limit jobs are envisaged through LSTK mode of execution while Outside Battery Limit (OSBL part such as tanks interconnections, utilities) is to be through the conventional mode. PFR has been prepared by IOCL itself on the basis of which TOR was granted for one unit but returned for the other. Find out more 8Also know more when PMC RFQs can be expected for these projects Click here for more details for the catalytic iso-dewaxing Click here for more details for the catalytic dewaxing unit