Software update: Fertilizer projects
Nov 18: SSP/NPK Greenfield Project
8Cost - Rs 70 crore
8Project Event: Project activities effected due to COVID-19, feasibility studies are ongoing, The company is planning to submit the proposal for the environmental clearance in December 2020 now, RFQ for the contractor is likely to be released in February 2021.
Single/Triple Super Phosphate Greenfield Project  
8Cost - Rs 30 crore
8Project Event: The proposal for environmental clearance was submitted in June 2018, and the proposal was accepted by SEAC. The project team has been made, RFQ for the contractor is likely to be released in Jan 2021.

**********************************