Software update: Fertilizer projects
Oct 13: 8Cost - Rs 6000 crore
 Find out who the L-1 bidder was for the Instrument Air System & Plant
Ammonia-Urea Energy Saving Project
8Cost - Rs 250 crore
8Project Event: The feasibility studies are still ongoing, which is likely to be completed in November 2021, RFQ for the LSTK contractor is likely to be re-released in Q3 FY 2021.
Ammonia-Urea Annual Maintenance Project
8Cost - Rs 20 crore
8Project Event: The NIT preparation is ongoing, RFQ for a registered maintenance contractor is likely to be released in December 2021.
Ammonia-Urea Annual Maintenance Project
8Cost - Rs 20 crore
8Project Event: RFQ for the different registered maintenance contractors is likely to be released in January 2022  

**********************************