Software update: Fertilizer projects
May 17: Ammonia Storage Tank Greenfield Project
8Cost: 100 Cr.
8Project EventThe RFQ for the ammonia storage tank with associated facilities has been out and the due date has been extended from 12 April 13 June 2022, due to lack of bidder.
Ammonia-Urea Energy Saving Project
8Cost: 250 Cr.
8Project Event: Still, All the project activities are on hold due to lack of funds, Capital approval is still under process. It is likely to be elicited in Q2 FY 2022-2023. RFQ for the LSTK contractor is likely to be released in Q2 FY 2022-2023.

**********************************