Software update: Fertilizer projects
May 19: Ammonium Nitrate Melt Greenfield Project
8Cost: 88 Cr.
8Project EventThe procurement work is ongoing for the equipment. L&T Hydrocarbon Engineering Ltd is the LSTK contractor, and the scope of work is Process license, Supply of Basic Design., Detailed Engineering, HAZOP Studies, and implementation of its recommendation, Procurement, and Supply of all equipment, Construction is likely to be started in Q2 FY 2022-2023.
Sulphuric acid Greenfield project
8Cost: 400 Cr.
8Project Event: RFQ for the LSTK contractor is likely to be released at the end of June 2022, due to a delay in internal discussion. The company has also signed technology partnership agreements with MECS (Monsanto Enviro-Chem Systems) and TKIS (ThyssenKrupp Industrial Solutions).

**********************************