May 20: Ammonia-Urea Expansion Project 8Cost: 150 Cr. 8Project Event: The company is still waiting for approval for the loan. The project has elicited environmental clearance in Jan 2020. RFQ for the EPC contractor is likely to be released in Q2 FY 2022-2023 due to delay in the internal discussion. Sulphuric Acid and Captive Power Unit Expansion Project 8Cost: 300 Cr. 8Project Event: The project is still awaiting environmental clearance, Public hearing has been completed. clearance is likely to be elicited in July 2022. Internal discussion is still ongoing. RFQ for the PMC contractor is likely to be released in Q2 FY 2022-2023.