Software update: Power projects
Nov 16: Rs 21400 crore  greenfield super thermal power project stage-1: Absorber system package in December 2022
8Erection of SG work has been delayed due to multiple leakages from the reheater tube.
8Re-tendering is yet to be started for the SG package.
8RFQ for the absorber system package is likely to be floated in December 2022.
Rs 11150 crore greenfield pumped storage project: Civil works package in Q1 2023
8The forest clearance stage 1 has been granted but stage 2 is pending at the nodal office
8PMC has been selected for the project.
8RFQ for the civil works package is likely to be floated in Q1 2023.
Rs 11500 crore greenfield pumped storage project: HM works package in Q1 2023
8EC, FC, and WL clearance have been obtained.
8The bid evaluation is in progress for EM works.
8RFQ for the HM works package is likely to be floated in Q1 2023
Rs 350 crore construction of 400 KV D/C project: T/L work in December 2022
8Approval from PTCC, Civil aviation, and defense have been granted.
8Erection and installation of substations are in progress.
8Bid evaluation is in progress for the P/S works.
8RFQ for the T/L work is likely to be floated in December 2022.