Software update: Fertilizer projects
Nov 18: Effluent Treatment Plant Up-gradation Project
8Cost: Rs 101 Cr.
8Project Event: 60% of construction work has been completed, the installation Electrochlorination System is ongoing, and commissioning is likely to be done in January 2023 in place of Nov 2022, due to delay in the construction. All the procurement work has been completed and all the long lead items have been reached at the site. Ion-exchange India Ltd is the LSTK contractor.
Nano Fertilizer Greenfield Project
8Cost: Rs 119 Cr.
8Project Event: The India' second nano fertilizer plant has been ready, production will start as soon as the government approves it. The plant is expected to be commissioned in December 2022, pre -commissioning is ongoing.

**********************************