Nov 23: Rs 15400 crore greenfield super thermal power project: Separator system in December 2022 8The project was further getting delayed due to the slow work progress by contractors in the air-cooled condenser 8Erection and installation of ESP have been completed 8RFQ for the separator system package is likely to be floated in December 2022 by EPC. Rs 680 crore greenfield pumped storage project: EPC package is likely to be floated in Q1 2023 8Forest clearance is not required for the project. 8DPR and EIA consultants have been selected. 8Geotechnical investigation and topographical survey have been completed for the project. 8RFQ for the EPC package is likely to be floated in Q1 2023 Rs 11,500 crore greenfield multipurpose project: SIA consultants is likely to be floated in January 2023 8The project was getting delayed due to issues with hydrology and DPR 8Preparation of new DPR is in progress. 8Consultant has been selected for EIA/ EMP study. 8RFQ for the SIA consultants is likely to be floated in January 2023. Get in touch with us for more on these project