Software update: Power projects
Nov 25: Rs 5000 crore Pumped Storage Project: Facing trouble
Find out why this project is running into trouble
8Yet preparation of packages is on
8Find out what kind of date has been set for the RFQ for the civil works package
 Rs:5700 crore Greenfield Hydro Electric Project: What kind of packages are meant to come?
A PMC has been selected for the Niare Greenfield Hydro Electric Project
8But will the tendering be on a package-wide mode or EPC mode
8Also know more on when the Civil works package (lot-1) is likely to be floated
Rs 4000 crore hydroelectric project: New promoter starts work after L&T drops out
8WAPCOS is preparing the DPR of the project. Application for forest clearance stage-1 is pending at the nodal office and wildlife clearance is pending at
8the wildlife warden. The consultant has started the preparation of the EIA/EMP report. Preparation of tender is in progress for the
8PMC package. Further bids are expected soon.
8RFQ for the PMC package is likely to be floated in Q1 2023.
Get in touch with us for more on these project


**********************************