Software update: Fertilizer projects
Nov 25: Urea Revamp Project
8Cost: Rs 700 Cr.
8Project Event:  Detailed Engineering is still ongoing by Fact Engineering And Design organization which is likely to be completed in Q4 FY 2022-2023. RFQ for the LSTK contractors is expected to be released at the end of Q4 FY 2022-2023
Single/Triple Super Phosphate Greenfield Project
8Cost: Rs 25 Cr.
8Project Event: RFQ for the local contractor is likely to be released in Q4 2023-2024, The project has elicited the environmental clearance, and internal discussion is still ongoing.

**********************************