Software update: Power projects
Nov 29: Rs 4550 crore brownfield thermal power project: Limestone and gypsum handling plant package in December 2022.
8PG test is yet to be conducted for BTG
8Railway sliding works are in the initial phase of their construction
8RFQ for the limestone and gypsum handling plant package is likely to be floated in December 2022.
Rs 2700 crore greenfield hydroelectric storage project: SIA consultant in Q1 2023
8TOR of the project has been granted.
8Bid evaluation is in progress for the EIA consultant
8RFQ for the SIA consultant is likely to be floated in Q1 2023.
Rs 4172 crore greenfield  pumped storage project: Civil works package in Q1 2023
8DPR and EIA report is yet to be approved by MoEF.
8The project got delayed as the villagers and environmentalists raised concerns over submerged and cultivated land.
8Forest clearance stage 2 is pending at the nodal office
8RFQ for the civil works package is likely to float in Q1 2023.