Nov 30: Rs 500 crore greenfield hydroelectric storage project: Electro-mechanical works in Q1 2023
8Construction of the approach road has been completed.
8Indian prime minister lays the foundation stone for this project.
8Tender has been floated for the civil and hydro-mechanical works.
8RFQ for the Electro-mechanical works package is likely to be floated in Q1 2023.
Rs 6200 crore greenfield hydroelectric storage project: Civil works (Lot -1) is likely to be floated in Q1 2023
8Forest clearance stage 1 has been granted but stage 2 is pending at DFO
8The private land owner of the three villages didn't accept the proposal for the land acquisition and the negotiation with the land owner is in progress
8RFQ for the civil works (Lot -1) is likely to be floated in Q1 2023.