Software update: Power projects
Mar 07: Rs 5800 crore greenfield hydroelectric multipurpose project: HM package coming up
8
Contractor has been selected for the civil works package.
8Mobilization of equipment at the site is yet to be started
8Private land acquisition has been completed
8RFQ for the HM package is likely to be floated in May 2023
 Rs 3300 crore greenfield closed-loop pumped storage project: EIA consultant package
8TOR of the project has been delayed due to a lack of a muck disposal plan
8RFQ for the EIA consultant is likely to be floated in Q2 2023
Get in touch with us for more on these project.


**********************************