Rs 80 crore gas gathering station-I: RFQs to start from mid-February, 2017
Dec 06: A business opportunity is coming up for a new Gas Gathering Station
8The cost of the project is Rs 80 crore
8Environment clearance is expected around May, 2017
8EOIs to be released by mid-February, 2017
8RFQ’S will float for the equipments of GGS by the end of April 2017
8Tenders for infrastructure development will be released by December end, 2016
The infrastructure development RFQs are to be for the following:
8Building construction materials
8Bulldozer
8Excavation Equipments
8Generators
8Land Clearing
8Paving and Permits
8Tractors
8Trucks
8Cementing Requirements