Software updates: Refinery tenders coming up
Jun 14: 8Project Name: Refinery Greenfield BS-VI Project
8Project Cost: Rs 3500 crore
8Project Event: RFQ for the piping work in the DHSD unit is expected by July 2018.
RFQ for the erection and installation work in the DHDS unit is expected by August 2018.
RFQ for the tankage and cooling tower jobs is expected by September 2018.
8Expenditure Approval: Q1:2016
8RFQ Date: July/2018
8Release Date: Aug/2018
8Start Date: May/2017
8Completion Date: Q2:2020
Click here for more details

8Project Name: Refinery Debottlenecking Project
8Project Cost: Rs 2500 crore
8Project Event: RFQ for commissioning and pre-commissioning work is expected by August 2018.
8Expenditure Approval: Q4:2016
8RFQ Date: Aug/2018
8Release Date: Sep/2018
8Start Date: Q2:2017
8Completion Date: Q4:2018
Click here for more details

8Project Name: Another Refinery BS-VI Greenfield Project
8Project Cost: Rs 550 crore
8Requirement: Major short lead equipment are: flanges, valves, strippers, reformer tubes, foot valves, auto recirculation valve, amine cartridge filters, torque wrenches, level switches, thermocouples, thermowells, antifriction bearing, spray nozzle, columns, heat tracing system, tube inserts, bolt tensioners, filters, desalters, scrubbers, strippers, separators, reactors.
8Project Event: RFQ for the short lead items is expected by August instead of July 2018.
8Expenditure Approval: Q3:2017
8RFQ Date: Aug/2018
8Release Date: Sep/2018
8Start Date: Q2:2018
8Completion Date: Q1:2021
Click here for more details


**********************************