Jan 03: The construction phase of the project is expected to start from Q-2,2017. The project schedule involves: 8Investigation Studies-6 Months 8Jetty Construction-18 Months 8FSRU Conversion-15 Months 8Onshore storage tanks-36 Months 8Regasification facilities-8 Months 8Truck Loading Stations-6 Months 8Dredging Activity-6 Months 8Unloading Arms-6 Months 8Gas Pipeline Connectivity-12 Months 8The project is expected to get commissioned in February, 2020. Click on Details for more