Feb 01: A jetty based Floating Storage Regasification Unit project has been proposed.
8The project will be taken up in two phases.
8Phase-I will consist of a jetty based FSRU of approximately. 4.0 mmtpa capacity.
8The FSRU is likely to operate purely on merchant model basis.
8In Phase-II, a land based regasification terminal with an ultimate capacity of 8.0 mmtpa has been planned.
8The finalization of a charter party contract for the FSRU is expected to take place early, by Q-1,2017.
8The company will initiate jetty construction work shortly to ensure timely completion of the project.
8The phase-I of the project is expected to be operational from Q2-2018.
8The total project(both the phases) is expected to commissioned by early,2020.