New ammonia- urea fertilizer complex: requirement of equipments
Feb 15: Constructionwork is going on and there is a requirement for equipment and services for agreenfieldproject of ammonia- urea fertilizer complex coming up in India witha capacityof 2200 TPD and urea 3850 MTPD of ammonia and urea respectively and a 28 MW Captive power plant 8Project commisisoning schedule is very tight with the date fixed currently for December, 2018 but it will be a challenge to stick to this timeline. 8The projected investment cost is Rs 6000 crore. Following are the requirement of equipments and services plant wise. 8Captive power plant 8Urea bagging plant 8Vacuum system. Click on Details for Key contacts and company details: