Software update: Rs 9181 crore Khargone Super Thermal Power Project
Jul 31: National Thermal Power Corporation along with EPC Contractor Larsen & Toubro - Sargent & Lundy and Sub-Contractor Netra Infra Tech Pvt. Ltd. continues with the construction of 1320 MW (2*660MW) Khargone Ultra Super Critical Thermal Power Plant in Khargone, Madhya Pradesh.
8L & T will itself carry out procurements for Boiler and Turbine and complete Balance of Plant in which auxiliaries for Boiler and Turbine will come from L & T. Sub-Contracts for Ash Dyke Package has been awarded to R K Transport & Construction and Induced Draft Cooling Tower has been awarded to Netra Infra Tech Pvt. Ltd.
8The owner is to come out with an FGD package soon.
8Project Event   RFQ for Flue Gas Desulfurization Unit is expected to be floated in 3rd Quarter of 2017.
8Completion Date:  January 2020