Software updates: Oil and Gas Projects
Mar 08: 8Project Name: Greenfield POL Terminal
8Project Cost: Rs 940 Crore
8Project Description: An owner is planning to install a new common user petroleum product storage and distribution terminal to be owned and operated by two other PSUs with a capacity of 143120 KL. Its TOR was granted by December 2017 and Environmental Clearance is expected by April 2018.
8Project Event: RFQ for the contractor is expected by May 2018.
8Expenditure Approval: Q1:2017
8RFQ Date: May/2018
8Release Date: Jun/2018
8Start Date: Q2:2018
8Completion Date: Q1:2019
Click here for more details.

8Project Name: POL Terminal Expansion Project
8Project Cost: Rs 226 Crore
8Project Description: An owner is planning to expand its POL storage capacity from 77,918 KL to 1,63,918 KL. A private company is hired as an EPCM contractor.
8Project Event: RFQ for equipment is expected by May 2018.
8Expenditure Approval: Q1:2017
8RFQ Date: May/2018
8Release Date: Jul/2018
8Start Date: Q3:2018
8Completion Date: Q3:2019
Click here for more details.

8Project Name: Greenfield LPG Bottling plant
8Project Cost: Rs 137 Crore
8Project Description: An owner is planning to install an LPG bottling plant with a capacity of 1050 MTPA by installing 3 X 350 MT mounded storage vessels for storage and 120 TMTPA bottling capacity.
8Project Event: RFQ for the PMC contractor is expected by May 2018.
8Expenditure Approval: Q1:2017
8RFQ Date: Jun/2018
8Release Date: Jul/2018
8Start Date: Q3:2018
8Completion Date: Q3:2020
Click here for more details.


**********************************