Mar 12: 8Project Name: Super Critical Thermal Power Greenfield Project 8Project Cost: 8000 crores 8Project Description: The owner's 1320 MW (2x660 MW) greenfield super-critical thermal power plant is on hold due to delay in getting coal linkage. Currently, the owner is in talks with SECL for coal linkage. EIA report has been revised for the greenfield project. The owner will come out with EPC contract soon. 8Project Event: RFQ for an EPC contract is expected by Q3 2018, instead of March 2018. 8Expenditure Approval: Feb/2018 8RFQ Date: Q3:2018 8Release Date: Q4:2018 8Start Date: Q3:2019 8Completion Date: Q1:2024 Click here for more information 8Project Name: Thermal Power Station - Dismantling 8Project Cost: 200 crores 8Project Description: The owner's dismantling work in the 135 MW (2x67.5 MW) coal based thermal power plant is getting hampered on account of delay in approval from the Government of NCT, Delhi. A consultant has been hired for carrying out survey activities. Further RFQs for dismantling services are expected soon. 8Project Event: RFQ for dismantling services of various equipment is expected by Q2 2018, instead of March 2018. 8Expenditure Approval: Q2:2017 8RFQ Date: Q2:2018 8Release Date: Q3:2018 8Start Date: Q1:2019 8Completion Date: Q2:2021 Click here for more information Contact Update : Contacts are an important tool in the hands of a business development manager. We put in great efforts to get you validated telephone numbers of departmental heads within the power industry. 8A general manager of project of a major NTPC's joint venture plant has moved to the major thermal power station. Click on details for more information