Software Updates : Power Projects
Mar 21: 8Project Name: Procurement of Dry Sorbent Injection system at Thermal Power Station
8Project Cost: 500 crores
8Project Description: The owner is planning the installation of a dry sorbent injection (DSI) system package for a 800 MW thermal power complex for monitoring and removal of all acid gas emissions. Further RFQs for DSI package are expected soon.
8Equipment required are : silo and reclaim system, weigh hopper and feeder, transport air blowers, proprietary injection lance design, and reagent milling.
8Project Event: RFQs for dry sorbent injection (DSI) system package are expected by Q2 2018.
8Expenditure Approval: Q2:2017
8RFQ Date: Q2:2018
8Release Date: Q2:2018
8Start Date: Q4:2018
8Completion Date: Q1:2020
Click here for more information
8Project Name: Greenfield Hydroelectric Project
8Project Cost: 800 crores
8Project Description: The promoter's 90 MW greenfield hydel project is getting hampered due to bad weather conditions and inconvenient approach road to the site. There is a delay in the hiring of an EIA consultant as of now.
8Project Event: RFQ for an EIA consultant is expected by Q3 2018, instead of Q1 2018.
8Expenditure Approval: Q4:2017
8RFQ Date: Q3:2018
8Release Date: Q4:2018
8Start Date: 2020
8Completion Date: 2025
Click here for more information
8Project Name: Thermal Power Plant - Dismantling Project
8Project Cost: 100 crores
8Project Description: The developer is planning to retire and dismantle Units 1,2 and 3 of it's 600 MW thermal power plant. RFQs for dismantling services are expected soon.
8Project requirements : elevators, cranes, scaffolding, demolition equipment among others.
8Project Event: RFQs for dismantling services of various equipment are expected by Q2 2018.
8Expenditure Approval: Q4:2017
8RFQ Date: Q2:2018
8Release Date: Q3:2018
8Start Date: Q1:2019
8Completion Date: Q2:2020
Click here for more information

**********************************