Software updates: Oil and Gas Projects.
Mar 26: Upto 5 Key Contacts are available for this project
8 Project Name: Development Drilling Project
8Project Cost: Rs 1000 Crore.
8Project Description: RFQs for promoter's 100 well development drilling plan have been delayed a bit. The TOR for the project has already been granted. The process of hiring an EPC contractor for 1 production installation and the 150 km pipeline laying part is expected to begin soon. RFQ for the Rigs, Blow-Out Controller, Xmas Trees, Cementing, Wireline, Drill Collar etc is expected shortly.
8Project Event: RFQ for EPC contractor for production installation and the pipeline network is expected by May instead of March 2018.
RFQ for hiring services for rigs and equipment is expected by May instead of April 2018.
8Expenditure Approval: Q2/2017
8RFQ Date: May/2018
8Release Date: Jun/2018
8Start Date: Q4/2018
8Completion Date: Q4/2020
Click here for more details

8 Project Name: Oil Field Development.
8Project Description: Promoter is planning the development of an oil field . The project involves development drilling of 3 oil wells, development of 2 existing wells and laying of an infield pipeline to connect with the nearest production facility (GGS). A requirement for PMC is expected from promoter's end for design and tendering process. Moreover, manpower requirement is also expected shortly. Further RFQs are expected shortly.
8Project Event: RFQ for hiring PMC consultant is expected by May instead of April 2018.
RFQs for manpower services are expected by November 2018.
8Expenditure Approval: Q4/2017
8RFQ Date: May/2018
8Release Date: Jul/2018
8Start Date: Q4/2018
8Completion Date: Q4/2019
Click here for more details
8Project Name: Drilling Field Development
8Project Cost: Rs 1200 crore
8Project Description: The Promoter is planning exploratory drilling of 70 wells in ML Blocks. The Targeted depths of proposed exploratory wells shall be up to 6500 M. The locations are proposed to be drilled by electrical type rigs which will be hired on EPC basis. The equipment required for the project will be casing pipes, drilling pipes, cementing services, drill bits, Xmas Tree and other oilfield chemicals. An EIA consultant has already been hired for the project. Further RFQs are expected shortly.
8Project Event: RFQ for the hiring of rig services is expected by Q3:2018.
RFQs for the equipment and oilfield chemicals are expected by Q3:2018.
8Expenditure Approval: Q3/2016
8RFQ Date: Q3/2018
8Release Date: Q3/2018
8Start Date: June/2019
8Completion Date: Dec/2021
Click here for more details


**********************************