Rs 150 crore bottling plant expansion: PMC contractor RFQ in June 2018; RFQ for refinery maintenance coming up as well
Apr 26: 8Project Name:  LPG Bottling Plant Expansion Project
8Project Cost: Rs 150 crore
8Project Description: Owner is planning to expand its LPG bottling plant.
8Project Event: RFQ for the PMC Contractor is expected by June 2018.
8Expenditure Approval : Q4:2016
8RFQ Date : Jun/2018
8Release Date: Jul/2018
8Start Date : Q3:2018
8Completion Date : Q3:2020
Click here for more details.

8Business Opportunity for Equipment Maintenance Contractor
8Owner is planning to float a bid for the equipment maintenance contractor involving Heat-Exchanger, Furnace, Vessels and piping job for its Hydrogen Generation Unit at the time of maintenance of the refinery