Software updates: Fertilizer projects
Apr 30: Ammonia-Urea Energy Saving Project  
8Cost - Rs 347 Crore
8Project Event: EOI has already been released for an LSTK contractor in November 2017 but NIT has not been floated yet, and s likely in May due to delays in the discussions.
Click here for more information
Naptha to Natural Gas Feedstock Conversion Project      
8Cost - Rs 250 Crore
8Project Event: Thermax, J& K, and Furnace Engineering are in the race for supply cum erection of NG Preheater (D1153) and NG feed Preheat Coil(D1206). The is likely to be finalized in May 2018.
Click here for more information


**********************************