Refinery Fuel Quality Upgradation Project: RFQ for installation work of Prime G+ unit is expected by August 2018
Jun 08: 8Project Name: Refinery Fuel Quality Upgradation Project
8Project Cost: Rs 1400 crore
8Project Description: The owner had hired an LSTK contractor, who along with the licensor, is carrying out the engineering activities to construct a new Prime G unit. On ground work is on.
8Project Event: RFQ for installation work of Prime G+ unit is expected by August 2018.
8Expenditure Approval: Q1:2015
8RFQ Date: Aug/2018
8Release Date: Sep/2018
8Start Date: Jul/2015
8Completion Date: Q1:2019