ONGC finally commissions Mehasana ETP project: Root cause analysis for delays is the immediate requirement
Jun 21:
ONGC's 3 ETPs at three locations (North Kadi GGS-I, Bechraji and Sobhasan GGS-II) of Mehsana Asset along with laying of associated pipelines and 7 years O & M contracts have finally been commissioned after a long gap of 4 years. 8We see signs of faulty planning and the use of a ham-handed all-size-fits-all contractor selection process by ONGC. 8Root cause analysis point to the late start of engineering by the contractor and delay in finalization of process package 8Will the E&P major do complete diagnostics on why such projects get delayed? Click on Details for more