Mathura Refinery Greenfield Bulk Import Of Grid Power Project: RFQ for the EPCM contractor for the OSBL work is expected October 2018
Aug 13: 8Project Name: Mathura Refinery Greenfield Bulk Import Of Grid Power Project
8Project Cost: Rs 256 crore
8Project Description: Indian Oil Corporation Limited is planning to develop the bulk import of grid power at 220 KV in its existing Mathura refinery. The project is divided into two parts Outside Battery Limit (OSBL) work and Inside Battery Limit (ISBL) work. Earlier the load demand was 45 MW but was revised to 72 MW. MN Dastur was appointed as EPCM contractor for the ISBL work in the month of May 2018, and currently, basic engineering and detailed engineering work are in progress.
8Project Event: RFQ for the EPCM contractor for the OSBL work is expected October 2018.
8Expenditure Approval: Q2:2017
8RFQ Date: Oct/2018
8Release Date: Nov/2018
8Start Date: Q2:2018
8Completion Date: Aug/2020