Rayagada LPG Bottling Greenfield Project: Contract goes to PDIL
Aug 14: Project Name:Rayagada LPG Bottling Greenfield Project
8Project Cost: Rs 92 crore.
8Project Description: Hindustan Petroleum Corporation Limited is constructing a new LPG Bottling Plant of 60 TMTPA capacity with a 24 filling guns automatic electronic carousal with downstream facilities, LPG mounded bullet storage of 3 x 300 MT, and four truck unloading bays and other allied facilities at Rayagada in Odisha.
8Project Event New: The company has been hired PDIL as an EPCM contractor in July 2018. Engineering work is yet to start. Equipment RFQs are expected subsequently.
8RFQ Date: Oct/2018.
8Release Date: Oct/2018
8Date: Feb/2019
8Completion Date: Feb/2021