New H2S unit replacement coming up: RFQ for LSTK contractor this month
Sep 06: 8Project Name: H2S Unit Replacement
8Project Description: The owner is planning the replacement of the Hydrogen Disulphide Unit (H2S) at its Gas Processing Plant. The project will be executed on LSTK basis and will also involve a maintenance contract for an overall period of six years.
8Project Event: Pre-qualification meeting for hiring an LSTK contractor is expected by 25th Sep 2018.
8Expenditure Approval: Q2/2018
8RFQ Date: 25/Sep/2018
8Release Date: Oct/2018
8Start Date: Q1/2019
8Completion Date: Q1/2020