Feb 27: Ammonia-Urea Brownfield Project
8Cost - Rs 6000 crore
8Project Event: The procurement & installation work is ongoing, RFQ for the bagging, buildings, wagon loading platform, conveyor gantry, transfer tower and pipe rack structure for ammonia-urea fertilizer plant has been released and bid due is extended from 31 January 2020 to 3 March 2020. The project is likely to be commissioned in December 2021.
Click here for more details

Urea Casale Revamp Project
8Cost - Rs 137 crore
8Project Event: The project has been delay by three months due to procurement work, all the equipment and services have reached the site. The revamp is likely to be implemented in April /May 2020 shutdown.