Software update: Linde's bid rejected
May 06:  There is contracting going on for a Rs 6000 crore ammonia-urea brownfield project
8For this package where Linde was the L-1 has been cancelled, its price was found to be too high
8Then again, in another package, BTL EPC, Macwaber Beekay & Tata Projects are shortlisted
8There is this Rs 200 crore coal-based ammonia greenfield project
8It is going to be set up on a BOO basis now
8And the bid date has been extended 