Software update: Power projects
May 24: This is a 12,000 crore greenfield thermal power plant
8Many contractors were involved, it is nearing commissioning
8But some RFQs are still left
Rs 3000 crore greenfield hydroelectric project
8RFQ for the drilling and drifting works is likely to float in July 2022.
8Get key contacts here
Rs 4000 crore greenfield Pump Storage Project
8Tender package preparation work is ongoing
8RFQ for the PMC package is likely to be floated in Q3 2022.
220 kV D/C  Transmission Line
8RFQ for the 220 kV P/S package is likely to be floated in June 2022.