Mar 14: Rs 6100 crore greenfield hydroelectric project: Land acquisition delayed
8The  private land owner of the three villages didn't accept the proposal for the land acquisition
8Bid evaluation in progress for HM packages,
8RFQ for the EM works package is likely to be floated in May 2023.
Rs 1600 crore greenfield hydroelectric project: EM package coming up
8Forest clearance stage-1 and stage-2 have been granted
8Bid evaluation in progress for HM packages,
8RFQ for the EM works package is likely to be floated in May 2023.
Rs 1550 crore greenfield multipurpose project: RFQ ahead
8HRT works are in progress
8Mobilization works are in progress for HM works.
8RFQ for the HM works is likely to be floated in Q2 2023