8Project Name: Spurline Pipeline Project
8Project Cost: Rs 25 crore
8Project Description: Gujarat Gas Limited is planning to lay a Natural gas spur line with a capacity of 1.29 MMSCMD along with the length of 19.1 Km for city gas purposes. It is envisaged that initially, the tap off connectivity shall be from GAIL Receiving Terminal. Gujarat Gas Limited has awarded the work to a private company for carrying out Reconnaissance Survey, Detailed Engineering Route Survey, Soil Investigation, Soil Resistivity and Cadastral Survey including obtaining Statutory Clearances and ROU Acquisition. Recently, a TOR was submitted but was returned on account of incomplete documentation.
8Project Event: RFQ for EPC contractor is expected by August 2018.
8Expenditure Approval: Q4:2016
8RFQ Date: Aug/2018
8Release Date: Sep/2018
8Start Date: Q1:2019
8Completion Date: Q4:2020
Click here for more details for more
Details
ONGC has the lowest finding and development (F&D) cost among 50 of its global peers.
8When lifting cost is taken into account, its total cost is the lowest among all 50
8The finding is remarkable, as 40 of its peers have an F&D cost of less than $35/bbl
Click on Reports  to know more 
Details
One local Jackup rig supplier seems has run into financial trouble
8Low hire rates, sometimes below fixed cost, and inability to find fixtures, for some of its rigs are the reasons behind the financial distress.
8Find out more on where its rigs are getting deployed and the losses that it is incurring
Click on Reports  for more
Details
Indian retail marketers must keep in mind the latest projections from none other than the IEA that the electric vehicle fleet can go up to a staggering 230 million units by 2030 from a mere 3 million now
8Projections for China, which is the clear front runner in this race, shows that under one scenario, more than 90% of its two wheelers will be electrified by then, around 40% of its cars and 65% of its buses.
8In comparison, India's targets have not been set. Indian investments in electric infrastructure is among the lowest in the world.
8But once the economics of electric vehicle turns positive, as it surely will at some time in comparison the internal combustion engine, the sector will see a massive surge of investment in India.
8In today's day and age, the catch up time is short.
8In scenario planning by oil companies including private sector companies planning on an aggressive roll out of its retail outlets, it will be necessary to take the Chinese numbers as the upper case and then project the impact on petrol and diesel demand even though IEA's projected numbers for 2030 for India are much lower.
Click on Reports  for more Details
One business space in the oil & gas sector that seems to face the most uncertainty is the private retailing of petrol and diesel.
8For one, projections are showing crude prices at $90/bbl in 2020.
8These prices would clearly mean that the political establishment, despite its bravado as of now, will end up imposing price caps on public sector oil companies. How much haircut would the oil marketing companies take is a matter of conjecture.
8But one thing is for sure, the hard fought market share increases by private retailers will get reversed
8Caught between high crude prices and the looming electric vehicle revolution, the next 10 years are going to be the most volatile for private retail in India.
8Retailers may have to find innovative ways to cross subsidize retail prices or find alternative revenue streams for their outlets if crude prices continue to stay high.
Click on Reports  for more Details
Phosphoric Acid Expansion Project   
8Cost - Rs 100 Crore
8Project Event: The EPC contractor is already selected and engineering work is ongoing, equipment and services purchasing are ongoing.
Click here for more information
Single Super Phosphate Greenfield Project       
8Cost - Rs 10 Crore
8Project Event: The proposal for an environmental clearance is likely to be granted in August 2018, The tender for an EPC contractor is likely to be released at the end of June or first week of July 2018.
Click here for more information
Sulphuric Acid Expansion Project     
8Cost - Rs 100 Crore
8Project Event: Major equipment purchase work is ongoing
Click here for more information
  Details
While ONGC has the lowest finding and development cost among its peers, it also been able to extract the lowest Jackup rig rates in the world
8The rates in fact have come down by exactly two thirds from what it was three years ago.
8Clearly, the company is pushing suppliers hard to extract such concessions.
Click on Details for more
  
Details
8Project Name: Early Production System
8Project Cost: Rs 250 crore.
8Project Description New: ONGC has changed its plans for building an Early Production System (EPS) that will be connected with 6 wells in an oil field. The proposed facilities in this project are HP Separator Skid, CO2, and Moisture Removal Skid, Dew Point Depression Skid, N2 Based Skid, Produced Water Storage and Bay Facilities and Other Utilities and Offsites. The equipment requirement will be Gas Turbine, Air Compressor, Storage tanks, Well Head, Water Injection Well, Flare Stack, Gas pipeline.
8Project Event New: RFQs for hiring EPC contractor for EPS is expected by September instead of June 2018. RFQs for hiring EPC contractor for the pipeline is expected by September instead of 2018.
8Expenditure Approval: Q2/2016
8RFQ Date: Sep/2018.
8Release Date: Nov/2018.
8Date: Q4/2018
8Completion Date: Q4/2019
Click here for more details for more
Details
8Project Name:  Development Drilling
8Project Cost: Rs 100 crore
8Project Description New: The owner has started accepting integrated rig services quotations for its onland development field. The project involves workover of 2 temporarily abandoned wells and development drilling 5 wells and laying of pipelines for connecting the oil field with a nearest production facility. The FDP for the block has not been submitted till now.
8Project Event New: RFQS for hiring pipeline services is expected by September 2018.
8Project Event Old: RFQ for hiring a consultant for EIA services is expected by June end instead of May end 2018.
RFQ for hiring rig and other oilfield services is expected by June instead of March end 2018.
8Expenditure Approval: Q2/2017
8RFQ Date: Sep/2018
8Release Date: Oct/2018
8Start Date: Q3/2018
8Completion Date: Q4/2019
Click here for more information for more
Details
8Project Name: CBM Development 
8Project Cost: Rs 1300 crore
8Project Description: The Promoter is planning  development drilling of 95 wells. The Project also involves the construction of 6 Gas Collecting Stations (GCS) and laying of interconnecting and transportation pipeline network (4”) for CBM transportation. One exploratory and two pilot wells were drilled during Phase-I and Phase-II respectively in the block and gave encouraging results for all the wells. All the planned wells are of vertical profile and promoter owned Drilling Rigs are proposed to be deployed for undertaking drilling activities. The expected reserves of the block are 43 billion cubic meters (bcm). The clearance has been granted recently and the promoter is planning to use lateral drilling technology in one portion of the block. The equipment required for the project will be Drilling pipes, Casing pipes, Drill Bits, Blow out Preventer, Directional Drilling services, Cementing services and Mud engineering services. Further RFQs are expected shortly. 
8Project Event: RFQ for the hiring of an EPC Contractor for GCS construction and laying of pipelines are expected by Q3:2018.
RFQ for the hiring of equipment and directional drilling services are expected by Q3:2018.
8Expenditure Approval: Q3/2014
8RFQ Date: Q3/2018
8Release Date: Q3/2018
8Start Date: Sept/2019
8Completion Date: Dec/2022
Click here for more details
Details
8Project Name: Thermal Power Station - Annual Maintenance Contract
8Project Cost: 5 crores
8Project Description: The joint venture company will come out with bid for O&M contract of an ash handling plant in the 1000 MW thermal power station.
8Project Event: RFQ for annual maintenance contract of an ash handling plant is expected by Q3 2018.
8Expenditure Approval: Q1:2018
8RFQ Date: Q3:2018
8Release Date: Q3:2018
8Start Date: Q4:2018
8Completion Date: Q4:2019
Click here for more information
8Project Name: R&M of  Hydro Power Station
8Project Cost: 23 crores
8Project Description: Owner is carrying out the remnant life assessment (RLA) studies in 135 MW hydro power station. Further RFQs are expected soon.
8Project Event: RFQs for supply, installation, erection and commissioning of a new digital governor are expected by the end of June 2018.
8Expenditure Approval: Q2:2017
8RFQ Date: 28/Jun/2018
8Release Date: 30/Jun/2018
8Start Date: Q1:2019
8Completion Date: Q1:2020
Click here for more information
8Project Name: Thermal Power Station - Installation of FGD
8Project Cost: 700 crores
8Project Description: The owner is planning the installation of flue gas desulphurisation units (FGD) in 3500 MW thermal power complex. Further bids are expected soon.
8Project Event: RFQs for supply, installation and commissioning of FGDs are expected by the mid June 2018.
8Expenditure Approval: Q1:2017
8RFQ Date: 16/Jun/2018
8Release Date: 20/Jun/2018
8Start Date: 2021
8Completion Date: 2023
Click here for more information
Details
The drilling contract was awarded to Schlumberger.
8Cairn India is about to spud the first Well of KG-OSN-2009/3 offshore block.
8Find out which Jackup rig has been hired for the job
Click on Details for more
   Details
KEI-RSOS Petroleum & Energy Pvt Ltd has been awarded the block KG/OSDSF/GS-KV1/2016 in KG Offshore Basin under DSF round-1.
8The Directorate General of Hydrocarbons (DGH) has approved KEI-RSOS Field Development Plan (FDP) for the GS-KV gas and GS-59 oil fields on the Krishna-Godavari Basin shallow water block.
8Under the FDP, the fields have an expected peak oil production of 200 bo/d and 0.5 MMcfg/d. First oil is scheduled for June 2020. KEI-RSOS Petroleum & Energy Pvt Ltd holds a 8100% interest in the block.
If you are looking for opportunities, click on Details for key contact Details
8Project Name: Greenfield LPG Bottling Plant
8Project Cost: Rs 100 crore
8Project Description: The owner is planning to install an LPG Bottling Plant with a capacity of 900 MTPA and an EIA consultant has been appointed. Further RFQs are expected soon.
8Project Event: RFQ for the PMC contractor is expected by August 2018
8Expenditure Approval: Q2/2017
8RFQ Date: Aug/2018
8Release Date: Sep/2018
8Start Date: Q4:2018
8Completion Date: Q4:2020
Click here for more details for information
Details
8Project Name :LNG Terminal Project 
8Project Cost: Rs 1200 crore
8Project Description: The owner is planning to install an LNG Floating Storage and Regasification Unit (FSRU).
8Project Event: RFQ for PMC contractor is expected by August instead of June 2018.
8Expenditure Approval: Q4/2016
8RFQ Date: Aug/2018
8Release Date: Sep/2018
8Start Date: Q4:2018
8Completion Date: Q3:2020
Click here for more details for more project configuration and key contacts
Details
8Project Name: Refinery INDMAX Project
8Project Cost: Rs 4300 crore
8Project Description: The owner has appointed an EPC contractor and along with the licensor, they are carrying out engineering activities for an INDMAX unit. RFQ for equipment is already out. At present civil work is going on. ThyssenKrupp has got the contract of mechanical work for the FCC unit. RFQ for the mechanical work for the NHT and SRU is already out.
8Project Event: RFQ for the mechanical work for the Catalytic Reformer Unit (CRU) and Selective Desulphurisation Unit (SDS) is expected by August 2018.
8Expenditure Approval: Q3:2016
8RFQ Date: Aug/2018
8Release Date: Sep/2018
8Start Date: Q4:2017
8Completion Date: Q2:2020
Click here for more details for more contacts
Details
8Project Name: LPG Bottling Plant Project
8Project Cost: Rs 150 crore
8Project Description: The owner is planning to set an LPG bottling plant by installing 3X600MT mounded storage bullets for storage of LPG with a bottling capacity of 60 TMTPA. RFQ for electrical and instrumentation work is already out.
8Project Event: RFQ for mechanical work is to be expected by July 2018.
8Expenditure Approval: Q3:2016
8RFQ Date: Jul/2018
8Release Date: Aug/2018
8Start Date: Q3:2018
8Completion Date: Q1:2020
Click here for more details for more information
Details
For reference purposes the website carries here the following tenders:
8Procurement of SC Valves Details
8Corrigendum: Supply of Motor Driven Daughter Booster Compressor package along with AMC Details
8Hiring of Services for NDT of Tubular, Handling Tools and Equipments of Drilling Services Details
8Hiring of Stimulation and Testing Services for wells Details
8ARC for maintenance of Control Valves and other Field Instruments for three years Details
8Engaging Engineering Manpower Assistance during refinery M and I Shutdown Details
8Procurement of 100 Litres Proving Vessel at Sankari Terminal Details
8Services for inspection of atmospheric crude oil storage tanks at refinery Details
8Annual Rate contract for pilferage restoration and maintenance work in mainline Details
8Annual Maintenance Rate Contract of O&M Jobs for Pipeline ROU and associated facilities in Pipeline Network Details
8Procurement of Coated Line Pipes Details
8Topographic, Geotechnical, Hydrological and Hydrographical Survey of Plots and Water Bodies for Natural Gas Pipeline Details
8Supply, Installation and Commissioning of Pre-fabricated Substation Details
8Procurement of Potassium Hydroxide Details
You can also click on Tenders for more 
For reference purposes the website carries here the following Newsclips:
8ONGC fourth quarter net profit up 36.2 per cent at Rs 5,915 crore Details
8Fuel price revision: IOC clarifies on erroneous price revision, cuts prices by 1 paisa after “glitch” Details
8Fuel price hike: Farmers protesting diesel rates hand over tractor keys to officials Details
8If 1 paisa cut in fuel price is PM Modi's prank, it is in poor taste: Rahul Gandhi Details
8Venezuela's PDVSA seeks imported fuel, offers fuel oil -traders Details
8Fuel price hike: IndiGo to levy fuel surcharge as jet fuel prices soar Details
8Fuel price hike: Kerala to cut taxes on petrol, diesel to reduce retail prices Details
8Britain's SSE to raise standard electricity and gas prices Details

8Moody's cuts India's GDP growth forecast to 7.3 per cent Details
8India fourth quarter GDP growth seen at 7.1 per cent: Ficci survey Details
8Iran's oil exports fall in May, when U.S. quit nuclear deal - Petro-Logistics Details
8Congress to start 'tweet morcha' on June 2 against fuel price hike Details
8Kerala cuts petrol, diesel prices by Re 1 per litre Details
8
Oil climbs over 2 percent, shrugs off API's U.S. crude build Details
8Crude one-paisa joke on petrol Details
8Reliance to halt oil imports from Iran Details
8India's growth likely topped 7% again in January-March quarter Details
8Government has no role in fuel price fixation: Oil Minister Details
8New study suggests 13 measures that can reduce air pollution by 40 pc Details
8Buffett utility to be first in U.S. to reach 100 pct renewables Details
8Oil prices dip on unexpected growth in U.S. crude stocks Details
8World Bank helps Bangladesh expand access to renewable energy Details
8Fuel price: Petrol price cut by 7 paise, diesel by 5 paise per litre Details
8Reliance Industries to halt oil imports from Iran from Oct-Nov Details
8Rupee opens 1 paisa higher against US dollar Details
8Petronet to partner OVL for stake in Qatar Petroleum LNG project – Mr Singh Details
8Efforts on to bring petrol, diesel under GST, says Dharmendra Pradhan Details
8'Mockery of pain' chant on fuel price Details
You can also click on Newsclips for more
Details
8Project Name: Super Thermal Power Greenfield Project
8Project Cost: 25000 crores
8Project Description: The EPC contractor is carrying out contracting activities for a 1980 MW super-critical complex. Further bids are expected soon.
8Project Event: RFQs for land leveling and grading works are expected by the mid June 2018.
8Expenditure Approval: Nov/2017
8RFQ Date: 16/Jun/2018
8Release Date: 20/Jul/2018
8Start Date: Q2:2019
8Completion Date: Q4:2023
Click here for more information
8Project Name: Thermal Power Plant - Annual Maintenance Contractor
8Project Cost: 2 crores
8Project Description: The owner is in the preparation of Notice Inviting Tender (NIT) documents for annual rate contract for electrical equipment in 2400 MW super-critical thermal power station. Further bids are expected soon..
8Project Event: RFQ for annual maintenance contract of electrical equipment is expected by the first week of June 2018.
8Expenditure Approval: Q1:2014
8RFQ Date: 10/Jun/2018
8Release Date: 13/Jul/2018
8Start Date: Aug/2018
8Completion Date: Aug/2019
Click here for more information
8Project Name: Thermal Power Station Maintenance Project 
8Project Cost: 8 crores
8Project Description: Owner has planned a 28-day annual scheduled boiler overhaul in the 2000 MW thermal power station. The mandatory work includes overhauling of ID and FD fans, replacement of boiler pressure parts, replacement of seals, among others.
8Project Event: RFQs for required equipment are expected by the July 2018.
Click here for more information Details
8Find out more on how L&T's domestic E&C is driving its growth. Click on Report  for more.
8HPCL: What does the future hold in store. Click on Report  for more.
8L&T Technology Services Ltd: Breaking new grounds. Click on Report  for more.
8A comparison of 4 years of Modi rule with that of four years of Manmohan Singh: Not great track record. Click on Report  for more.
8Lastest gas demand and supply data. Click on Report  for more.
8Latest crude import and domestic production data. Click on Report  for more.
8Latest data on LPG consumption and production. Click on Report  for more. Details
As oil prices rise, it is very easy for an oil company to lose perspective the dramatic and far-reaching changes in his business environment triggered by the advent of renewable energy.
8Historical evidence seems to indicate that energy transitions are slow but this particular current transition may be much faster.
8This transition is being managed and coordinated through government policy aimed at decarbonization and reducing air pollution, whereas past transitions happened mostly naturally or accidentally without strong policy support.
8This means that the drivers of the current transition are fundamentally different from the past transformations and this induces uncertainty about how events could unfold.
8The transition this time around will be faster and quicker than anything that has happened before.
8For an oil company, moving beyond its core business is highly risky but at the same time a ‘wait-and-watch' strategy can be extremely costly.
8In this perspective, find out more about what strategies can an oil company adopt to be future ready
Click on Reports  for more Details
Up until this decade, the business strategy of oil and gas companies was straightforward: replace or grow reserves, refine and sell products as the market expands
8As oil demand prospects have become more uncertain and traditional energy sources face disruption, oil companies need a different approach.
8The alternative approach, however, is not straightforward.
8One option seems to be to move from oil to gas, a strategy adopted by top oil companies, but this is fraught with risks as well
8Moving outside of the oil & gas industry is never going to be easy as RIL is finding out.
8The IRRs just do not match up to what is achieved in its core competencies. Staying within them while being flexible with its options, could perhaps been a better choice.
8If the transition was so simple, large oil & gas players such as BP and Exxon Mobil or the Chinese super majors, with piles of cash much larger than RIL, would have quickly added retail and phone companies to their portfolios.
8In this context, it is important to take sock of the segments that an oil & gas company get into as the future becomes increasingly uncertain?
Click on Reports  to find out more. Details
In the context of energy transition,  is RIL's breakneck entry into the retail and mobile industries been the right strategy?
8Could it have planned differently?
8Should it have transited so far away from its core competencies?
8The company's refining segment, while being highly competitive, is still at risk because of the ongoing global transition in this segment.
8The petrochemical industry will stay on track but the future choice of raw material and energy will eventually be of critical importance as increasingly aggressive low cost players and disruptive technological changes come into play.
Click on Reports  for more  Details
Oil & gas companies always tend to look at carbon pricing as a battle between gas vs. coal. If carbon prices are raised, it will benefit gas as it is a cleaner fuel than coal
8But the latest 2018 report on how carbon pricing is developing does not augur well for the oil & gas industry
8Deep structural changes are taking place, and these will have huge future implications
8Multiple trends are emerging in terms of how the public and private sectors are employing carbon pricing and these provide an indication of how carbon pricing could possibly unfold in the future.
Click on Reports  for more Details
8Armed with a 10-year extension of its PSC, Oilex has now served a notice on GSPC to acquire its stake in the block
8This is not a negotiated settlement but an aggressive bid to take over the stakes on the ground of non-payment of cash calls
8Find out more on which way this story is going
Click on Reports  Details
 Ammonia - Urea & Captive Power Plant Greenfield Project       
 
8Cost - Rs 10000 Crore
 
8Project Event: Internal discussion process for hiring an EPC contractor is going on and RFQ for a contractor is likely to be released in next week.
 Click here for more information
 NPK Fertilizer Greenfield Project      
 
8Cost - Rs 1517 Crore
 
8Project Event: RFQ for EPC contractor was floated in February 2017 and price bid has opened. Finalization is due in July 2018 due and tender for equipment is likely to be released in August 2018.
 Click here for more information 
The fertilizer sector is seeing a huge increase in investments. We provide a 100% coverage of all outstanding projects in this segment. Please speak to our marketing department for more details
Details
8Project Name: Oil Field Exploratory Drilling
8Project Cost: Rs 1200 crore
8Project Description New: The owner plans to drill 48 wells in 13 PML Blocks. The wells are expected to be drilled up to a depth of 4000 meters. The wells will be expected to be drilled using ONGC owned rigs. The environmental clearance for the project has already been granted. The requirements will be a mobile Effluent Treatment Plant, Casing pipes, Drilling pipes, Drilling Mud, Cementing services, Drilling fluid services and other oilfield chemicals.
8Project Event New: RFQ for the requirements is expected by August instead of June 2018.
8Expenditure Approval: Q2/2018
8RFQ Date: Aug/2018
8Release Date: Sep/2018
8Start Date: Oct/2018
8Completion Date: Q4/2022
Click here for more information
Details
8Project Name: CBM Block Development
8Project Cost: Rs 500 crore.
8Project Description: The JV has already awarded an integrated drilling services contract. Moreover, a contract has been signed  with another company for supply of equipment and services for the block. A US firm is doing consultancy work. Pipeline services quotations are currently being accepted for the block.
8Project Event New: RFQs for hiring crane services is expected by August 2018.
8Expenditure Approval: Q1/2016
8RFQ Date: Aug/2018.
8Release Date: Sep/2018.
8Date: Q4/2018
8Completion Date: Q3/2021
Click here for more details for more information
Details
8Project Name: Greenfield LPG Import Terminal Project 
8Project Cost: Rs 800 crore
8Project Description: Owner is planning to set up an LPG terminal for supplying gas to its bottling plants. Earlier, the project was on hold but now the terminal has received environmental clearance as well as clearance from the Petroleum and Explosive Safety Organisation.
8Project Event: RFQ For EPC contractor is to be expected by August instead of June 2018.
8Expenditure Approval: July:2014
8RFQ Date: Aug/2018
8Release Date: Sep/2018
8Start Date: Q4:2018
8Completion Date: Q1:2020
Click here for more details for more
Details
8Project Name: Greenfield Pipeline Project
8Project Cost: Rs 1600 crore
8Project Description: Owner has hired Worley Parsons as an EPCM contractor Further RFQs are awaited.
8Project Event: RFQ for FEED work is expected by August 2018.
8Expenditure Approval: Q3:2017
8RFQ Date: Aug/2018
8Release Date: Sep/2018
8Start Date: Q3:2018
8Completion Date: Q4:2021
Click here for more details
Details
8Project Name: Tie-in-Connectivity Pipeline Project
8Project Cost: Rs 45 crore
8Project Description: A port is planning for Tie-in-Connectivity from a proposed LNG terminal to a trunl gas pipeline network.
8Project Event: RFQ for the PFR consultant is expected by August 2018.
8Expenditure Approval: Q3/2017
8RFQ Date: Aug/2018
8Release Date: Sep/2018
8Start Date: Q1:2019
8Completion Date: Q2:2021
Click here for more details
Details
8Project Name: Naphtha Cracker Unit Project
8Project Cost: Rs 1500 crore
8Project Description: The owner is planning expansions of its Naphtha Cracker Unit including associated units. A licensor has been appointed.
8Project Event: RFQ for centrifugal & reciprocating compressors, centrifugal & reciprocating pumps, Columns, Valves, Heat excangers, feed pumps, Reflux drums, Reactors, Nozzles, Emergency shutdown valves, level transmitters, level sensors, mixing tanks with agitators, flow meters, vessels, regenerator, main fractionator, propylene splitter, flanges, strippers, motors, reformer tubes, foot valves, auto recirculation valve, torque wrenches, level switches, thermocouples, thermowells, antifriction bearing, transformer, heat tracing system, spray nozzle, columns, tube inserts, bolt tensioners is expected by July 2018.
8Expenditure Approval: Q4/2016
8RFQ Date: Jul/2018
8Release Date: Sep/2018
8Start Date: Q4:2018
8Completion Date: Q2:2022
Click here for more details
Details
8Business Opportunity for Pipeline Contractor
The owner is is planning to float an annual rate contract for mechanical and pipeline jobs in the KG basin. The scope of work include supplying of gas to consumers in three districts East- Godavari, West- Godavari and Krishna of Andhra Pradesh. The job duration will be of two years and extended to six months more. Click on Details for key contacts
8ONGC pushes DeenDayal block: Launches 5 EOIs. Click on Details for more Details
For reference purposes the website carries here the following tenders:
8Installation and commissioning of Pressure Transmitter and Differential Pressure Transmitters Details
8Comprehensive Annual Maintenance Contract of Access Control System installed at various points refinery Details
8Integrated Seismic Job Service and Shot Hole Drilling Services for 3D Seismic Data Acquisition Details
8Hiring of 10 MT Forklift for Nhava Supply Base Details
8Procurement of Pipe Fittings and Flanges Details
8Supply of Temperature Gauges for refinery Details
8Lining up of Managed Security Services (MSS) for Refineries Head Quarters Details
8Supply of Caustic Soda Lye at refinery Details
8Supply of Ethyle Mercaptan in refinery Details
8Carrying out PCP works under Pipeline Section Details
8Hydro-testing and Long Term Preservation of Insurance Line Pipes Details
8Procurement of Gate, Globe and Check Valves in refinery Details
8ARC for carrying out Mechanical and Pipeline Jobs Details
You can also click on Tenders for more 
For reference purposes the website carries here the following Newsclips:
8FPI debt selling hits 18-month high in May Details
8A petrol, diesel price solution for 'future' might be on the cards Details
8Petroleum ministry clears proposal for petrol, diesel futures Details
8Fuel prices rise for the 16th consecutive day, NITI Aayog deputy chief suggests tax cut Details
8Gas trading hub may come up by year-end: petroleum board Details
820 districts in Telangana to have piped gas Details
8Assam: Oil India achieves 72.27% growth in 2017-18 Details
8IndiGo announces fuel surcharge to counter rising oil prices Details

8Fuel price hike - People angry with rising petrol prices, urge Govt to tackle hike Details
8ONGC nominates one director on HPCL board; wants common govt director Details
8How the world's biggest private equity oil and gas industry bid collapsed Details
8India's maiden Gas Trading Hub to be functional before Dec: PNGRB Details
8Sebi to vet petrol & diesel futures contracts launch Details
8
Rising fuel prices hit transportation cost of industries by 15 per cent Details
8New swamp: Lobbyist tied to Perry seeks energy firm bailout Details
8BPCL fourth quarter net profit up 45 per cent at Rs 2,674 cr Details
8City gas distributors’ share in gas consumption on the rise: India Ratings Details
8More than half of Telangana may get PNG and CNG Details
8COLUMN-Oil prices tumble as hedge funds quit crude: Kemp Details
8Tullow Oil picks Australia's Worley Parsons for Kenya contract Details
8Shipper BW LPG offers to buy Dorian LPG in $1.1 billion deal Details
8Azerbaijan inaugurates $40 bn European gas pipeline Details
8Finally, petrol and diesel prices fall across the country after 16-day surge Details
8IGL passing on oil surge a positive for city gas players Details
8Achieving Self-reliance in Oil and Gas Details
8Relief at last? IOC cuts petrol price by 60 paise, diesel by 56 paise Details
8Focus on India’s long term macroeconomic story Details
8Oil falls on threat of OPEC boost; funds quit crude Details
8BPCL will be watched after Q4 results Details
8Petrol, diesel prices cut after 16 days as crude oil softens Details
You can also click on Newsclips for more
Details
As LNG prices soar, is this really the end of the road for gas based projects?
While existing gas based units feel the pinch, there are new players contemplating getting in. Here are a few examples:
8A power generation company has dropped plans for installation of an imported coal-based 1320 MW (2x660 MW) project with super-critical technology but the owner could not proceed further due to curtailment of coal export by some countries and also due to the high tariff of power to be generated. In the meanwhile, the promoter is seeking to change the project configuration from a coal-based 2x660 MW super-critical thermal plant to a 1050 MW gas based combined cycle plant at the same location due to the availability of Regassified Liquefied Natural Gas (RLNG). Find out more about what he has in mind, including the gas supplier he is talking to
8Then again, another power company has decided to permanently shut down its aging coal-based power plants and set up two 660 MW supercritical units instead but this plan too had to be dropped due to pollution issues. The owner is now exploring the possibility of a gas-based power station instead. Discussions are going on for the supply of gas with a supplier. Know more about both the power project owner and the gas supplier, and if you are a gas supplier find out whether you can also speak to the owner.
Click on Details for key contacts
Details
Green solutions are increasingly available to handle the crucial challenge when when paraffin wax, asphaltene and resin deposition downgrades your pipeline flow rates, flow size, while increasing drag, significantly straining your production systems.
8Innovative new high-tech green tech molecular disaggregators are now available that effectively controls waxes, asphaltenes and resins at a lower dosage rate whilst dramatically reducing BS&W by rapid in-line separation of the water and oil phases, breaking emulsions and eliminating foam.
8New green technologies are now increasingly used instead of harmful chemicals.
8In India, such technology will be particularly helpful in the following assets:
Mangala Field Area & Pipeline: The Mangala field area contains an OOIP of 3.6 billion barrels & daily production of 200,000 bopd of waxy crude. If applied downhole, new molecues could resolve severe wax deposition problems. Then again in the 670 km pipeline transporting the crude is heated to 650C (the Wax Appearance Temperature) to keep the crude liquid. New molecules could be applied continuously in the pipeline to lower the WAT.
Mumbai High: The offshore Mumbai High Oil field is India’s largest containing ~half of India’s recoverable reserves. Current production is >200,000 bopd of waxy crude.The crude pour point (300C) is much higher than sea floor temperature creating flow assurance issues in the subsea pipelines. Green injections could be applied to lower the crude PP in the pipeline.
Assam: The Assam region produces ~30 million barrels of oil per year. Assam crude has a PP of 300C, much higher than average winter temperatures at surface,creating handling, storage & transport problems that could be resolved using green technology.
The point to note is that the new technolgies which are coming in are
organic, requires no harzardous chemical handling protocols (with a flash point of 97°C) and can significantly impact on your HS&E concerns and OPEX spend.
Click on Reports  for more
Details
Digital twin technologies are minimizing the need for testing efforts, which are usually cost-intensive and time-consuming.
8A comparison of the sensitivities calculated by the digital model on the construction of new flow meters, for example, obtained during field tests revealed an agreement of 95 percent – establishing the model as a realistic and accurate predictive tool
8Besides predicting sensitivity, the model could predict linearity of the flowmeter or in other words, constancy of the sensitivity with changing flowrates measurement accuracy.
8Not only is the digital twin concept an asset during the testing phase, the model has been extensively leveraged to modify the existing design of the flowmeter to improve quality.
8By incorporating novel component designs and innovative ideas in the model, improvement in flowmeter performance could be evaluated.
8The modified flowmeter was found to outperform the existing flowmeter product besides setting the stage for future design improvements.
8A new word of innovation has now opened up as a result
Click on Reports  for more
Details
Find out when new tenders are going to come up to replace the following offshore rigs under deployment with ONGC:
8C.E. Thornton MLT 53-SC 300
8F.G. McClintock MLT 53-SC 300
8Harvey H. Ward F&G L-780 Mod II 300
8J.T. Angel F&G L-780 Mod II 300
8Parameswara BMC 300-IC 300
8Trident II MLT 84-SC Mod 300
8Trident XII BMC 300-IC 300
Click on Reports for more   Details
Our research has shown that if you are looking for a Jackup rig, one is available right now at rock bottom rates
8The offer is that it will be provided the lowest rate available for a similar sized rig anywhere in the world
8Mobilization rates will be low as it is available as of now in Indian waters
Click on Details for more Click on Report  also for more.
   Details
Ammonia-Urea Energy Saving Project  
8Cost - Rs 481 Crore
8Project Event: The proposal for a term of references has been granted by the environmental ministry.The basic engineering study has not started yet and tender for equipment is likely to be released in June 2018.
Click here for more information
Single/Triple Super Phosphate Greenfield Project
        
8Cost - Rs 30 Crore
8Project Event: Tender for an EPC contractor is likely to be released in July 2018.
Click here for more information
Phosphoric Acid Greenfield Project       
8Cost - Rs 10 Crore
8Project Event: Final EIA report has been submitted and a public hearing is likely to start in June 2018 and Tender for an EPC contractor is likely to be released in July 2018.
Click here for more information
  Details
8Project Name: Oil Field Development
8Project Cost: Rs 400 crore
8Project Description: The owner is planning development drilling of 04 wells in Assam. The project also involves the construction of GCS and the laying of underground 3.5” seamless pipelines. from well BU-2 to BK-1, including interconnecting pipelines of 4 additional wells to be drilled. Owner owned electrical type rig is proposed to be deployed for undertaking drilling activities. The construction of GCS and laying of the pipelines will be done on EPC Basis. The equipment required for the project will be Drill Pipes, Casing Pipes, Xmas Trees, Blow Out Preventer, Cementing services and Drilling fluid services. An EIA consultant has already been hired for the project. Further RFQs are expected shortly.
8Project Event: RFQs for an EPC contractors for GCS, pipeline installation and oilfield chemicals is expected by Q3/2018.
8Expenditure Approval: Q2/2016
8RFQ Date: Q3/2018
8Release Date: Q3/2018
8Start Date: Oct/2019
8Completion Date: Dec/2021
Click here for more details for key contacts
Details
8Project Name:  Platform Trunkline Modification
8Project Cost: Rs 80 crore
8Project Description New: ONGC is planning modification in its existing BPB Platform Hazira Trunkline  Six companies have participated in the EOI. The gas pipeline supplies gas from offshore process platforms to the Gas Processing plant.
8Project Event New: RFQs for hiring an EPC contractor for the pipeline is expected by Q4 2018.
8Expenditure Approval: Q3/2018
8RFQ Date: Q4/2018
8Release Date: Q4/2018
8Start Date: Q1/2019
8Completion Date: Q4/2019
Click here for more information for more contacts
Details
8Project Name: Field Redevelopment
8Project Cost: Rs 1500 crore.
8Project Description New: Owner is currently conducting techno-commercial bid evaluation for a 4000 m3 ETP in the project that involves drilling of 140 wells, revamping and upgradation of 2 GGS-cum-CTFs in the field and construction of a new ETP Effluent Treatment Plant (ETF) of 4000 m3/d capacity. The LOI for the ETP is expected by June end 2018. The LSTK contract for the revamping of the GGS-cum-CTFs has alredy been awareded. Moreover, the tender for the Adapter and Adapter Spool is already out and is expected to be procured to vest on BHEL. The drilling part of the project would be done by the owner itself. Further requirements from the company's end will be for Xmas Trees, Couplings, Wireline and Cementing Services.
8Project Event New: RFQs for equipment expected by August instead of June 2018.
8Expenditure Approval: Feb/2017
8RFQ Date: Aug/2018.
8Release Date: Sep/2018.
8Date: Q4/2018
8Completion Date: Q4/2020
Click here for more details for more contacts
Details
For reference purposes the website carries here the following tenders:
8Procurement of Glutaraldehyde for MH Asset Details
8Supply of Pipes Fittings and Flanges as per technical specification at refinery Details
8Coating refurbishment of mainline valves Details
8Supply of Spares for Gas Turbines Details
8Annual Maintenance Contract for Mechanical Maintenance and allied jobs Details
8Supply of Amine phosphate Details
8Supply of Mechanical Seal Spares in refinery Details
8Supply of Level transmitters spares at refinery Details
8Procurement of Pipelines Details
8ARC for carrying out Scaffolding, Erection and dismantling jobs Details
8Supply of Motor Operated Actuators for Gate Valves of Launcher Details
You can also click on Tenders for more 
For reference purposes the website carries here the following Newsclips:
8Northeast to be connected with gas pipeline Details
8Maximise oil/gas, not government revenue Details
8Crude oil prices, dollar rates causing fuel price hike: Dharmendra Pradhan Details
8India says no plans for oil trade with Venezuela using 'petro' cryptocurrency Details
8CNG prices raised by 3.3 per cent in Delhi Details
8Petrol price crosses Rs 86 per litre mark rising for 15th straight day Details
8Oil ministry gives nod to petrol, diesel futures Details
8Petrol price hike: Measures to help you cut your car's petrol, diesel bill Details

8Fuel prices surges for 15th day, touches Rs 78.27 in Delhi Details
8PM Modi says 45 per cent of PMUY LPG connections went to Dalit households Details
8China Energy Reserve defaults on $350 million bond payment Details
8Tokyo shares struggle to maintain gains; falling oil prices drag on energy names Details
8Asia energy firms dive with oil, Trump-Kim hopes provide optimism Details
8
L&T fourth-quarter net profit up 4.9 per cent at Rs 3,337 crore Details
8Oil India fourth quarter net profit jumps 46 times to Rs 867 crore Details
8Petrol price hike - Holistic strategy to find long-term solution to fuel prices: Pradhan Details
8States can cut petrol price by Rs 2.65/litre by giving up additional gains: Report Details
8Petrol price hike: SBI economic body suggests measures to reduce fuel prices Details
8Fuel Price Hike: HPCL responds to questions on record rally in petrol, diesel rates Details
8Sebi close to clearing petrol, diesel futures Details
8Crude shock: Rising prices may take a toll on grocery bills Details
8PM tells Odisha housewife: Address me directly for any problem under Ujjwala Yojana Details
8Congress to protest against petrol price hike Details
8French renewables output soars in April, nuclear and fossil fuels decline Details
8Fuel prices may fall on sliding crude, rising rupee Details
8We see opportunity in renewables, smart cities: SocGen deputy CEO Details
8BEE signs pacts for promoting energy efficiency standards Details
8New record high for fuel prices: Petrol touches Rs 86.24 per litre Details
8Indraprastha Gas raises prices of CNG by Rs 1.36 per kg in Delhi Details
8State oil companies' capex jumps 22 per cent in FY18 Details
You can also click on Newsclips for more
Details
8The block was awarded as part of the NELP-VII Bid Round
8The block is located close to ONGC’s B-12 field
8Further RFQs are expected by Q4:2018.
Click on Details for more Details
FPSO is expected to be delivered by Q2 2021
8Find out which companies have been issued the tender
Click on Details for more Details
8Project Name: LNG Terminal Expansion
8Project Cost: Rs 2500 crore
8Project Description: A 5 MMTPA capacity is sought to be built
8Project Event: RFQ for the FEED work is expected by August 2018.
8Expenditure Approval: Q3:2017
8RFQ Date: Aug/2018
8Release Date: Sep/2018
8Start Date: Q4:2018
8Completion Date: Q4:2021
Click here for more details for more information, including key contacts and full project parameters
Details
8Project Name: Greenfield 2G Bio Ethanol Refinery Project
8Project Cost: Rs 800 crore
8Project Description: The owner is planning to construct an ethanol plant indigenously
8Project Event: RFQ for the BEDP services is expected by August 2018.
8Expenditure Approval: Q3:2017
8RFQ Date: Jul/2018
8Release Date: Aug/2018
8Start Date: Q4:2018
8Completion Date: Q3:2021
Click here for more details for project configuration and key contacts
Details
8Project Name:  LPG Bottling Plant Expansion Project
8Project Cost: Rs 200 crore
8Project Description: The owner is planning to expand its existing LPG bottling plant from 1000 MTPA to 2800 MTPA.
8Project Event: RFQ for equipment is expected by July instead of May 2018.
8Expenditure Approval: Q2/2017
8RFQ Date: Jul/2018
8Release Date: Aug/2018
8Start Date: Q3:2018
8Completion Date: Q3:2019
Click here for more details for key contacts
Details
8Project Name: Greenfield Hydroelectric Project
8Project Cost: 3500 crores
8Project Description: Owner is carrying out the survey and investigations activities for a 300 MW greenfield hydroelectric project. Further bids are expected soon.
8Project Event: RFQs for drilling and drifting works are expected by Q3 2018.
8Expenditure Approval: Q1:2019
8RFQ Date: Q3:2018
8Release Date: Q3:2018
8Start Date: 2020
8Completion Date: 2026
Click here for more information
8Project Name: Thermal Power Expansion Project
8Project Cost: 11000 crores
8Project Description: Promoter along with an EPC Contractor has completed the land leveling and grading activities for a 1980 MW super-critical project. Further tenders are expected soon.
8Project Event: Tenders for erection and installation of ash handling plant is expected by Q3 2018
8Expenditure Approval: Q1:2017
8RFQ Date: Q3:2018
8Release Date: Q3:2018
8Start Date: Q2:2017
8Completion Date: Q4:2021
Click here for more information
8Project Name: Thermal Power Station Maintenance Project
8Project Cost: 12 crores
8Project Description: A JV company has planned a 30-day scheduled overhaul in the 2000 MW thermal power station. The mandatory jobs includes replacement of boiler pressure parts, checking of generator rotor, replacement of guide bearings of turbine, among others.
8Project Event: RFQs for overhaul of equipment are expected by the end of June 2018.