Even as the prospect for LNG demand in India does look very bright in the short to the medium term, the outlook for Pakistan and Bangladesh has been raised 8Bangladesh is set to join the club of importers next year 8And projections are that LNG imports by Bangladesh may stand at a massive 25 MMTPA by 2025 Click on Reports for moreDetails
With breakeven prices for deepwater projects now falling from $ 70 to $ 40-50/bbl, the projections on deepwater incremental output going up to 2020 has been revised 8Of the total incremental new gas production, a larger chunk is to come from deepwater wells in relation to shallow water and onshore production 8The bulk of the incremental output, however, will continue to emanate from infill dirlling Click on Reports for more dataDetails
The advent of electric cars is meant to cause demand to begin a downward slide 8But when is that going to happen remains a moot point 8While some say that the point of inflexion can happen sooner than later, there are a lot of others who say that this point is not coming anytime soon Find out more why that can be so. Click on Report.Details
Saudi Arabia’s then Oil Minister Ali al-Naimi had once said that “whether it goes down to $20, $40, $50, $60, it is irrelevant,”. This was when Saudi Arabia had tried to run US shale producers to the ground by driving the price as low as possible 8Ali al-Naimi's strategy did not work and he lost his job. 8Saudi Arabia, in the face of quickly declining foreign exchange reserves, is trying to shore up the market by leading production cuts 8The website carries here an interesting picture of declining crude prices in relationship with the decline in Saudi foreign exchange assets 8But the battle is not over yet between US shale and Saudi oil Click on Reports for moreDetails
8Details of the government's plans to promote city gas distribution projects in Rajasthan. Click on Report for more. 8Vedanta's $ 1 billion capex plan in the Barmer field in hope of a 10-year extension to its license. Click on Report for more. 8Government's pricing and allocation plans for subsidised products in India. Click on Report for more. 8Details of ONGC's payments to GSPC for the KG-OSN-2001/3 field and the additional payments for other discoveries in the block. More payments will be due in the future. Click on Report for more. 8Find out more on how dispenser specifications are being changed in retail outlets to make them temper proof. Click on Report for more. 8A profit profile of oil companies over the last three years. Click on Report for more. 8Financial performance of ONGC, OVL and MRPL for quarter ending June, 2017. Click on Report for more. 8A presentation on ONGC's overall activities. Click on Report for more. 8Find out why ONGC is a "buy" as of now. One of the risks is a write-off of the Mozambique investments of around $ 4 billion, according to one analysis. Click on Report for more. 8VAT and excise duty components in RSP of petrol in four major cities in the country: Wide variations. Click on Report for more. 8Cost of BS-VI fuel transition is going to cost Indian refineries Rs 29750 crore.Click on Report for more. 8State-wise LPG connections as on July 27 under PMUY. Click on Report for more. 8Report of the sub-committee on land subsistence in Andhra Pradesh due to gas production in adjoining fields. Click on Report for more. 8Latest Indian basket of crude prices. Click on Report for more. 8Linking Aadhar to LPG connections: How is it going. Click on Report for more. 8Petronet LNG in talks for an LNG terminal in Mauritius. Click on Report for more. 8List of existing and under construction gas pipelines, along with capacity and length and states through which they traverse. Click on Report for more. 8Weekly holiday proposal by retail outlet owners: Government's view. Click on Report for more. 8Financial results of IOC. Click on Report for more.Details
8Project Name: Jakhol Sankri Greenfield Hydroelectric Power Station 8Project Description: SJVN is planning to construct a 51 MW Jakhol Sankri Hydroelectric Power Station near village Jakhol in district Uttarkashi of Uttarakhand. EIA studies are ongoing at present. The company is expected to apply for EC by April 2018 (tentatively). 8Major requirements will be: Dam and Barrage construction, Cofferdam, Generator, 2 vertical Pelton turbines, Control Equipment, 4 Vertical Gates, EOT Crane, Desilting Tank, Steel-lined Penstock (ASTMA-537 Class-2), Surge Shaft, Butterfly Valve, Transformer, Tunnel, TBM (tunnel boring machine), Steel Pipes, Transmission lines, Substation among many others. 8Project Cost: 460 Crore 8Project Event: RFQ for EPC contractor expected to be floated in January 2018. 8Project Name - Obra 'B TPS' Thermal Power Maintenance Project Click here for more 8Project Description - UPRVUNL has planned an 18-day Scheduled Mini Overhaul of Unit-10 'B TPS' (200 MW) in the 1188 MW Obra Thermal Power Plant. 8Key equipment which are needed for the maintenance are turbine bearings, HP, IP, LP turbine cylinders, motor winding, boiler linings, safety valves, nozzles, motor bearings, feed pump, rotor blades, fixed blades, circuit breakers, relays, fuses, pipes, conveyor belts, bucker wheel and vibro feeder moor in stacker reclaimer, sensors, among others. 8Project Event - RFQs for equipment required in Mini Overhaul of Unit-10 in Obra Thermal Power Plant is expected to be float in 2nd week of August 2017. 8Shutdown date - 2017-11-10 8Revival date - 2017-11-27 Click here for more.Details
8GCS Expansion 8Project Description: An expansion of a GCS facility is planned by an E&P company. 8The main equipment requirements in this project will be:- Gas Scrubber, Gas Filter, Flare KOD, Flare Stack and Tip. 8Project Event: RFQs for the mechanical equipment is expected in the month of October 2017. 8RFQ Date: Nov/2017 8Release Date: Jan/2018 8Start Date: Mar/2018 8Completion Date: May/2019 Click here to go to our software 8Brownfield Refinery Expansion 8Project Cost: Rs 3886 8Project Description: Owner along with PMC-cum-EPCM contractor is carrying out engineering activities to expand refinery capacity by 2 MMTPA. Environmental Clearance was granted on 31 January 2017. At present, Civil work is going on. 8Major equipment required are: vessels, columns, heaters, air cooled heat exchangers, pumps, strainers, air preheaters, shell & tube heat exchangers, compressors, ejectors, fired heaters, fans, filters, feed mixers, naphtha superheater, air coolers, blowers, reactors, flame arresters, motor operated valves, reflux drum, strippers, regenerators, condensers, valves. 8Project Event: RFQs for mechanical works are expected by September 2017. 8Expenditure Approval: Q4:2016 8RFQ Date: Sep/2017 8Release Date: Nov/2017 8Start Date: Jan/2017 8Completion Date: May/2019 Click here to go to our softwareDetails
8Rs 1500 crore greenfield NPK fertilizer plant: Today is the bid closing date 8Rs 4800 crore investment plan for Pesticide unit: Gas demand pegged at 1808185 Nm3/Day 8Rs 10,000 crore phosphoric acid plant: Tender for LSTK contractor in October 2017 Click on Details for project description and key contactsDetails
For reference purposes the website carries here the following tenders: 8Supply, Installation, Erection, Testing and Commissioning of Effluent Treatment Plant Details 8Supply of Heat Exchangers for BS-VI Project Details 8Supply of Radar Level Transmitters Details 8Civil works at drill site GKAG_Z in Geleky area Details 8Procurement of Tube Bundle for Heat Exchanger of Wet Gas inter stage trim cooler and Absorber Reflux Condenser Details 8Supply of ATF for Helibase and Nhava Supply Base Details You can also click on Tenders for more For reference purposes the website carries here the following Newsclips: 8Why India doesn’t need to worry about oil prices in near future Details 8BPCL increases commission offered to dealers upto 50 per cent: CMD D Rajkumar Details 8Bharat Petroleum Corporation Ltd to venture into gas biz: CMD D Rajkumar Details 8Thai oil refiner IRPC's quarterly profit slumps on stock loss Details 8Indian Oil, partners look for cheaper site for Pacific NorthWest LNG terminal Details 8Petrol pump dealers' commissions hiked by up to 60 per cent Details 8Oil dips on high OPEC supplies, defying falling U.S. crude stocks Details 8Oil majors gushing in cash despite cheap crude Details 8OPEC crude exports hit record high in July Details 8IOC first quarter net profit down 45 percent, GRM halvesDetails You can also click on Newsclips for moreDetails
8Reliance awards key R-Series subsea package -- OneSubsea offers 'competitive' price to beat the competition and lift contract for work on deep-water gas development off India's east coast, according to sources. -- They added that several other major contracts related to the R-Series development are expected to be awarded within the next week or two weeks. 8BP has been working hard to improve margins: New projects should deliver on average 35% better operating cash margins compared to the base portfolio in 2015 and around 20%, on average, lower development costs. In 2017, unit production costs to be more than 40% lower than in 2013. Around 75% of these cost reductions are from efficiency, so these should be sustainable in the longer term. Can ONGC use these parameters as some kind of a yardstick to benchmark their own performance. Click on Report for more. 8Kochi Shipyard's plans in India. Click on Report for more. 8Find out why India's LPG imports are going to rebound soon. Click on Report for more. 8Use of petroleum coke as an additive in metallurgical coal: A paper. Click on Report for more. 8Fresh exploratory finds by OIL India in Upper Assam. Click on Report for more. 8Latest price of India's basket for crude oil. Click on Report for more. 8Second wave of LNG supply is already coming online. Click on Report for more. 8Wipro wants to make a splash in oil & gas: Find our more. Click on Report. 8Kerala is making headway in clearing ROW for GAIL pipeline. Click on Report for more. 8Bangladesh goes for a huge power push. Click on Report for more. 8How cut in production by OPEC is not impacting the shipping market much. Click on Report for more. 8Arbitration in Panna Mukta Tapti fields: ONGC's take. Click on Report for more.
Details
8Project Name: Neyveli TPS II Second Expansion 8Project Description: NLC India Ltd is planning to add a supercritical unit of 1320 MW (2*660 MW) to it's existing 1970 MW (9*210 MW) Neyveli Thermal Power Station II at Neyveli in Cuddalore district of Tamil Nadu. The project received TOR on March 23, 2017. Presently, EIA report preparation is under process. An EPC contractor is expected to be hired in the first half of 2018. 8Major requirements will be steam turbine, generator, cooling tower, steam pipelines, pumps, transmission lines, substation, coal handling plant, ash handling plant, electrostatic precipitator among many others. 8Project Event: RFQ for EPC contractor expected in November 2017 Click here for more 8Project Name: Mawphu Hydroelectric Greenfield Project 8Project Cost: Rs 940.20 Cr. 8Project Description: North Eastern Electric Power Corporation Limited along with contractor Energy Infratech Pvt Ltd is writing out a DPR for a greenfield 85 MW Mawphu Hydroelectric Plant at Mawphu, East Khasi Hills, Meghalaya. However protest from amongst the people is the area is a matter of concern. Tendering for equipment required for Civil Work will be floated only after getting Environmental Clearance. Among major equipment which will be required will be hydro-mechanical equipment such as penstock, spillway, tailrace tunnel, headrace tunnel, pressure shaft, surge shaft and electro-mechanical equipment such turbine and generator and power house equipment in the next 6 months. 8Project Event: RFQs for civil works are expected by 1st Quarter of 2018. 8Expenditure Approval: Q2:Apr/2015 8RFQ Date: Q1:Jan/2018 8Release Date: Q1:Feb/2018 8Start Date: Q3:Sep/2018 8Completion Date: Q3:Sep/2023 Click here for moreDetails
Exploratory drilling project 8Project Cost: 780 crore. 8Exploratory drilling of 25 wells. The environment clearance for the project was granted on 19th April, 2017. 8Currently the civil works and rig preparation phase is going on. 8Existing rigs will be deployed for the job. Event: The RFQs for the mechanical equipment are expected by the mid August 2017. Click here for moreDetails
One of our most effective business development tools is our phone validated contact list of decision makers in the industrial segments that we cover. 8We go to extraordinary lengths to give you at least 5 to 8 key contacts (solely responsible for projects) within each company, facility and unit or project 8The onus of implementing a project moves from an owner to the contractor, and we shift our focus accordingly, giving you a list of phone validated contact numbers for every contractor associated with a project 8We understand that striking a deal is all about building relationships with the right people at the right time. 8So not everyone figures in our contact list. We pick and chose departmental heads who you can talk business with. Among the departments that we keep track of within a given industrial facility are: 8Facility in-charge 8Purchase in-charge 8Engineering in-charge 8Projects in-charge 8Logistics in-charge 8HSE in-charge 8IT in-charge 8We also have contact lists within every unit within a facility. There is an independent contact list too for the company or for headquarters. Having a valid contact list within a running project is of paramount importance. We give you the right onsite names of the: 8Manager representing the owner 8Manager representing the EPC or PMC contractor 8Manager representing the various sub contractors in the project Our attempt is to give you an adequate information matrix on upcoming business opportunities at the pre-tender stage.Details
Our research team works relentlessly to identify upcoming as well as ongoing capital and maintenance projects in India on an ongoing basis, allowing us to offer you the most up-to-date project data base in the country. 8We follow projects right from the early planning states till completion. Every project is constantly reviewed and validated in accordance with moving milestones to ensure the accuracy of information. 8Upcoming requirements for equipment and services are highlighted so that suppliers have an adequate advance warning. 8Our analysts spend the largest amount of time validating a contact database so that viewers just need to pull out a contact from the database and call Key data points for a project are: 8Planning to Commissioning schedules (multiple tracking from pre-feasibility to commissioning) 8Milestone events and dates (Capital approval, RFQ date, release date, start and completion dates) 8Key project developments 8Project requirements for key equipment and services 8Project contractors and sub contractors and their equipment and service needs 8Key project decision makers 8A detailed archiving system for individual projects Project search parameters include: 8Sector specific or through NIC codes 8Project status, type, stage and phase 8Investments 8Contractors 8Milestone events & dates 8Searchable project descriptions and equipment requirements 8Energy sources 8RFQ datesDetails
If you are a supplier of equipment or services to the oil and gas industry, your search for a business development opportunity has now become easier 8All you have to do is put in the equipment or service in the search parameters and our software will throw up all future projects in the power, fertilizers and oil & gas segments where there a requirement for it. 8What you get is the project description, essential project parameters and key contacts, which are validated by our team every three months. 8You can look for projects with RFQ dates a month, six months or one year from now. 8All you have to do is pick up the phone and call 8The point to note is that none of this information is top down. All of it is generated by our engineers from bottom up, through a laborious process of finding contacts, calling them up and validating all the information that we put up 8This is a first-of-its-kind project monitoring tool in IndiaDetails
Dispel your doubts on a project and check out the rumors. Just get across to our in-house team of analysts. Talk to them and they will check out the facts and get back to you. Our analysts are available between 9.30 AM to 6.30 PM IST, Monday through Friday. And all you have to do is to call them. 8Primary collection of project related data is conducted by trained engineers at our back end. We usually spend weeks training an engineer on the fine art and skills of collecting information. 8So whenever you speak to one of our analysts, he will most likely be aware of much more than what is available in the database. Do check him out. 8We admit that data collection for projects is a vast exercise and it may not be possible to find all the answers from our analyst. 8But if you were to ask him to clarify a rumor you have heard or a fact that you want double checked, just get across to our analyst. He will check it out for you and get back to you. You can check out the following facts about a Project: 8Validation of RFQ dates 8More details on equipment and service requirements 8Information on possible forward movement in case of delay Another set of contacts than those already given 8Change in commissioning date 8Likely capital approval date in case of planned projects 8Extra information on maintenance schedules You can find out more about Facilities and Units in terms of: 8Energy matrix 8Technology in use 8Raw material consumed or likely to be in demand 8Intermediate and finished product data 8Maps and directions 8Key contactsDetails
Our design and actual capacity matrix for products and raw materials and intermediates used by individual industrial units provides a first-hand and very accurate estimate of incremental all-India demand in a given industrial segment. 8We can tell you when and where exactly the demand for a particular commodity will fructify. 8The information can be sliced into industrial sub-segments, or further segregated in terms of demand emanating from specific facilities, units, geographies, operators and promoters. 8We can tell you when exactly demand will emanate from an industrial unit, giving a supplier adequate time to get in touch with the promoter and pitch for supply contracts. 8We can provide a progress report on new capacities coming up which will require raw material supplies. We can tell you whether the project underpinning the demand has passed the capital approval stage and how much longer it will take to be commissioned when the demand for raw materials will emerge. This will give you a better grip on the timelines by when commissioning will take place. 8This tool is very useful for suppliers of energy products such as fuel, gas or electricity. Big industrial enterprises require large volumes of energy and accurate projections help suppliers to plan better. 8Our contact data base accurately collects information on people in charge of purchases in facilities and units and allows a supplier to directly get in touch with potential buyers.Details
We provide accurate and fully validated investment estimations in the segments we are present. 8We have a unique bottom-up approach, where our engineers collect information from the ground level to build the macro investment picture. The estimation model therefore is much more accurate than a top down methodology. 8Using modeling, our data can be extrapolated further to provide you five and 10-year predictions. 8The investment data can be sliced into industrial sub-segments, and further segregated in terms of specific facilities and units, geographies, operators and promoters. 8Bankers and insurance companies will find this information of great help, when searching for clients looking for funding 8We can tell you how much investment has passed the capital approval stage, how much is under basic and detailed engineering, how much is under contracting and commissioning. 8We can project the size of the maintenance pie within a sector or sub-sector. 8Out software can disaggregate overall investments into many smaller sub-components to provide clients with a multi-faceted picture. 8It can a valid third party tool to keep track of projects in which banks and financial institutions have loaned money Suppliers of equipment and services: 8They can plan better when they get a fully disaggregated picture of how investments are going to pan out. 8They can target specific business opportunities, particularly for investments which have not reached the RFQ stage, either at the level of the promoter or contractor 8Our contact database can be tapped to zero in on specific managers handling these investments within corporate entities Suppliers of energy products: 8Accurate bottom-up estimation of fresh demand for energy in new capacities that are coming within an industrial sector.Detailed energy matrices in every industrial facility allow suppliers to save on time and research to zero in on the right opportunity 8A fully validated contact list allows the supplier to immediately get in touch with a potential client Banks and Financial Institutions 8Look for new clients requiring funding from our database of those promoters whose investments are at the planning stage but have not received capital approval 8Our contact database provides an easy way to directly get in touch with promoters Government and research institutions 8Accurate way of validating overall investment data 8Conduct further modeling from our disaggregated data Details
8Rs 800 crore synthetic Organic Chemical unit: Proposal to be submitted for clearance in September, 2017 8Rs 540 crore urea expansion cum energy saving project: Tender for equipment in October 2017 8New SSP expansion project: Tender for contractor in November 2017 Click on Details for more, including key contactsDetails
For reference purposes the website carries here the following tenders: 8Civil Works for preparation of cluster location for "MDDE" Site from existing site in Madanam Area Details 8Procurement of Intrinsically Safe Ultrasonic Thickness Meter for refinery Details 8Examining Feasibility of Design ,Fabrication, Transportation and Installation of Suction Piles for Offshore Well Head Platforms in Gulf of Kutch in Western Offshore Details 8Supply of carbon steel pipes for refinery Details 8Procurement of pipe fittings for refinery Details 8Procurement of Alloy Steel Flanges for 26 Refinery Vessels Project Details 8Procurement of Carbon Steel Flanges for 26 Refinery Vessels ProjectDetails You can also click on Tenders for more For reference purposes the website carries here the following Newsclips: 8BS VI: Challenges and opportunities for India’s auto industry Details 8Indian Oil Corp aims to source a tenth of oil demand from own assets Details 8Bharat Petroleum orders first taste of WTI Details 8After diesel and LPG, government to now end subsidy on kerosene Details 8GAIL begins construction of stalled Kochi-Mangaluru pipeline Details 8Market round-up: Coal India’s targets for FY18 unlikely to be met Details 8U.S. crude, gasoline and diesel stockpiles fall -EIA Details 8CAG raps MRPL for deficiencies in execution of Rs 16,323 crore expansion project Details 8China defends gasfield activity in East China Sea Details You can also click on Newsclips for moreDetails
We have evolved an elaborate reporting system for all shutdowns and turnarounds in our project software for the oil & gas sector. The moment our team picks up any shutdown data in the industry, we try and record the following parameters: --Shutdown cause -- Shutdown type -- Shutdown status -- Capacity offline -- Percentage of capacity offline -- Shutdown duration -- Shutdown date -- Expected restart date -- Previous shutdown date -- Previous restart date 8We will attach all the available information relating to the unit under shutdown and the industrial facility under which the unit is contained. 8All our units and facilities have multiple data points, involving technology details, input-output matrices, utility indices and key contacts 8If it is a planned shutdown, we provide a project along with it, providing key requirements of equipment and services as well information on RFQ dates and owner or contractor contacts. 8If it is an unplanned shutdown, we may not have time to build a project around it but we will get you the unit and facility data along with the alert beside information on key equipment that may require modification or replacement. 8There is a business development prospect with every shutdown and that is our key area of focus.Details
8New SSP plant: No response to a tender for contractor 8New ammonia- urea fertilizer complex: Environment clearance granted 8Technical pesticide unit: Tender for gas likely in October 2017 8Find out when will Chambal's new ammonia-urea plant will go onstream: When will 2 mmscmd of gas demand will come up? 8New 800 TPD SSP unit coming up Click on Details for more, including key contactsDetails
One of the reasons why ENI was able to get its project off the ground at a reasonable cost was because it promoted a floating LNG system. 8Anadarko however is not changing its initial project configuration 8Even though there are those who claim that the model must should be changed to take into account market realities 8Upstream and downstream links perhaps do not allow Anadarko to make such changes Click on Reports and Details for moreDetails
Deep Industries says that it will fight ONGC's terminal of contract 8The company acknowledged that the contracts have been canceled 8They are exploring all legal options to contest the termination Click on Reports for moreDetails
An EPC contractor is currently under selection for an onshore LNG terminal in India 8Cost of the project: Over Rs 5000 crore 8EIL had done the FEED and at present, EPC contractor selection process is under progress. Major equipment required are: boil off gas compressor, high pressure LNG pump, gas engine generator, tube LNG vaporizer with air heater and submerged combustion LNG vaporizer, among others. Project Event: RFQs for major equipment are expected to be floated by the selected EPC contractor by September, 2017. Expenditure Approval: Q1:2017 RFQ Date: Sep/2017 Release Date: Nov/2017 Start Date: Q4:2017 Completion Date: Q2:2019 Click here for more, including project description, key owner contacts and other relevant data.Details
We are carrying here a shutdown report of a power plant. The following data is given for the Rihand Super Thermal Power Maintenance Shutdown 8Shutdown cause: Mechanical 8Shutdown type: Planned 8Shutdown status: Ahead 8Capacity offline: 500 MW 8Unit offline: Unit-4 8Percentage offline: 16.66 8Breakdown duration: 30 days 8Facility involved: Rihand Thermal Power Station (Link available to see complete facility data) 8Plant involved: Unit-4 (Rihand STPS) Stage 2 (Link available to see complete unit data) 8Expected revival date: 12/12/2017 8Expected shutdown date: 13/11/2017 Along with the alert, we create a business development opportunity Project Name - Rihand Super Thermal Power Maintenance Project Project Cost- 11 cr Project Description - NTPC has planned a 30-day Scheduled Maintenance of Unit-4 (500 MW) in the 3000 MW Rihand Super Thermal Power Plant covering Boiler, LP Turbine & Generator Relay Protection auxiliary parts. Equipment requirements are: Boiler : Boiler feed control valve, boiler feed check valve, fuel oil pump, fuel oil heater, fuel oil duplex filters, fuel oil burners, soot blowers, safety valves, pipes, nozzles, economizer. LP Turbine : Governor system, rotor blades, fixed blades, nozzles among others. Generator Relay Protection : Lightning arrestor, differential relay, excitors, carbon brushes, sensors, among others. Project Event - RFQs for Boiler, LP Turbine & Generator Relay Protection auxiliary parts in Unit-4 of Rihand Super Thermal Station are expected to be floated in 3rd week of August 2017. Shutdown date - 2017-11-13 Revival date - 2017-12-12 Breakdown code – 7000000172 Click here for moreDetails
Now that a final investment decision (FID) has been taken for the ENI promoted Coral Floating LNG in offshore Mozambique underpinned by Shell's commitment to offtake all production, consortium leader Anadarko Petroleum has begun work on activating its own LNG project in the adjacent Rovuma Area 1 Offshore block in which the Indian trio of ONGC, Bharat Petro Resoures Ltd (BPRL) and Oil India Ltd (OIL) are involved. 8Anadarko announced that it had finalized two agreements with the Government of Mozambique – together known as the "marine concessions" – which would allow it to design, build and operate the marine facilities for its LNG project in northern Mozambique. This follows the publication of the Mozambican Government Decrees approving those agreements. 8But it will be a long while before FID can take place. Click on Details for moreDetails
ONGC has canceled two of its contracts with Deep Industries for gas dehydration units on the basis of allegations of a contractual misdemeanor. 8The cancellation may simultaneously put into action a blacklisting process within ONGC for the company from future projects. 8The company may subsequently be put on "holiday", sources said. 8Although the entire blacklisting process is currently confined to ONGC, it may well be possible that other public sector companies will also debar Deep from participating in future tenders if a blacklisting is carried through in ONGC 8A big chunk of Deep's business emanates from ONGC Click on Details for moreDetails
For reference purposes the website carries here the following tenders: 8Manpower supply for Wellsite Supervision during well testing/ Workover Operations in Operatorship Block, CB-ONN- 2010/8, Cambay Basin Details 8Supply of DHDT & VGO-HDT Bellis Turbine Spare at refinery Details 8Supply of Hydrochloric Acid Details 8Hiring of Services for 3D Seismic Data Acquisition and Processing of Jaisalmer PML Area in Rajasthan Details 8Procurement of Tube Bundles for Naphtha Stabilizer Condenser Details 8Adequacy Study of TPS High Pressure Boilers for its capacity enhancement at refinery Details 8Support Services during Pigging of Offshore pipelinesDetails 8Civil works for providing liquid nitrogen facility Details You can also click on Tenders for more For reference purposes the website carries here the following Newsclips: 8Petrol pump dealers' commissions hiked by up to 55% Details 8Be ready to pay more for petrol, diesel Details 8Iran oil exports rise 45,000bpd in July Details 8ONGC finds gas, oil offshore west and east India Details 8Some India coal utilities may miss emission goals, risk shutdowns: CEA Details 8Crude oil price slips from two-month high as ample supply weighs Details 8Tripura seeks review of daily price change module for petroleum products Details 8Maharashtra may hike fuel prices, says All India Petroleum Dealers Association Details 8BP sees oil prices below $50 a barrel in 2018 Details 8European oil majors seek to harness U.S. offshore wind energyDetails 8Airtel Payments Bank, HPCL tie-up for digital payments Details 8India refiners outshine Asia peers with new output, rising local demandDetails 8Domestic LPG price hike to help Modi govt save Rs 30,000 crore of annual subsidyDetails 8Arvind Panagariya resigns as Niti Aayog Vice Chairman Details You can also click on Newsclips for moreDetails
A worrying point that needs highlighting is the GITPL's assertion that there are "significant adverse changes in market demand" that is threatening the viability of the Mallavaram-Bhilwara-Vijaipur natural gas pipeline. 8The 1800 km pipeline will traverse through 33 districts and six states 8GITPL also claims that it will be able to cut down tariff drastically: gas from the KG basin can travel to NFL's Vijaipur plant at 25% of the current applicable tariff 8But the point is what is what has changed about gas demand in the heart of industrial India through which the pipeline winds it way? 8Clearly, demand for gas has not been found to be as buoyant as was anticipated earlier. 8The inability of cross-country pipelines in India to stay viable needs a further investigation. The market for gas is becoming more dynamic, with a plethora of competing fuels as crude prices continue to stay low. 8LPG, FO/LSHS and Pet Coke are competing with gas for the attention of dual feed furnace owners. Low cost renewable energy may also increasingly emerge as a competitor. 8Undoubtedly, India should ordinarily have an insatiable appetite for gas but when will demand emerge remains a moot point. 8Will disruptive changes -- such as lower for ever crude prices or the advent of electric car or really low cost renewable energy -- kill this demand before it emerges? 8The jury is still out on this subject. Click on Reports to find out more
Details
Beware of the ides of June, with apologies to the Roman saying. 8The disappearance of growth in POL consumption in the industrial sector in June is a sure of sign of distress that industry watchers must take cognizance of. The following data proves the point: 8Naphtha consumption declined 4.3% in June in relation to the same month last year. there has been a degrowth of 3.4% during April-June as well 8FO and LSHS consumption was down 12.9% in June and 7.7 % in April-June 8Petcoke, a low cost favorite among furnace owners in India, declined a massive 18.6% in June and 1.1% in April-June 8LDO consumption recorded a de-growth of 5.6% and 1.1% 8Was this slack in liquid fuel or feedstock production picked up by higher gas consumption? Not really 8Gas consumption grew only 0.75% in June and 0.63% in April-June 8The data supports the fact that core sector industrial growth slowed down to a 19-month low of 0.4%, much lower than 7% recorded in June, 2016 8Is it just the adverse impact of demonetization or is it a deeper more insidious peril looming around the corner? Click on Reports for more
Details
8The latest official position on what is being called "violation of the contract signed for oil and gas production in Krishna Godavari (KG) Basin which has come to the notice of the government recently". Click on Report for more. 8State-wise data that shows ethanol blending coming down from 3.5% in 2015-16 to 2.44 in July, 2017. Click on Report for more. 8Steps taken by companies to prevent a repeat of the GAIL pipeline blast that killed 22 people in their sleep in Andhra Pradesh. Click on Report for more. 8Farmers in Kerala are not just agitating against the laying of gas pipelines, they are opposed to LPG terminals as well. Click on Report for more. 8Steps taken by the DGH to monitor oil and gas production by national oil companies from their nomination blocks. Click on Report for more. 8Latest oil and gas development initiative by Cairn in its Barmer field. Click on Report for more. 8Valuation exercise on the upcoming merger of ONGC with HPCL: Why private sector could have given a much higher price. Click on Report for more. 8Latest update on LPG consumption and distribution in India. Click on Report for more. 8Details of three patents won by ONGC on hydrogen use in India. Click on Report for more. 8A break-up of the Rs 30,000 crore expenditure budget of ONGC. Click on Report for more. 8OVL commits $ 11 billion for the Farzad field, says it will settle for any "reasonable return" that Iran can guarantee: But has it come too late?. Click on Report for more. 8Are you involving with trading of LPG and gas in a public sector company? There is a Singapore based opening for an LPG trader with 10 to 15 years of experience. Click on Report for more. 8Latest government update on CNG usage in India and how to promote its growth New polices for use of kerosene in India: Details. Click on Report for more. 8A write up on the Empire Industries, a supplier of goods and services to the oil and gas industry. Click on Report for more.
Details
Deregulation was meant to help oil companies get out of the morass that they had slipped into 8But who has really benefited from deregulation in India? 8It is only the private sector, argues one paper 8The public sector had gained little or nothing, it goes on to argue Click on Reports for more
Details
Even as industrial POL consumption slows and goes negative, the transportation sector continues to thrive, albeit at a slightly slower pace 8MS consumption during June, 2017 recorded a robust growth of 11.9% and 10.6% in April-June, 2017 8Diesel consumption grew 6.5% and went up cumulatively to 5.8% 8Rapid vehicle growth is attributed to these consumption figures 8Air travel continues to soar: June ATF consumption grew 9.2% while in April-June, the increase was 9.9% 8So even as the industrial consumption tanks, the transportation segment continues to see growth. Click on Reports for more
Details
A tug of war is on between GAIL and GSPL India Transco Ltd (GITPL) over who should have the rights to transport gas from ONGC's Odalarevu terminal from where the E&P gas major's KG Basin gas output is to come in. 8GITPL is implementing the cross-country Mallavaram-Bhilwara-Vijaipur natural gas pipeline and it claims that one of the major reasons why it was set up was to ferry gas from ONGC's offshore KG Basin fields, such as the S1 and VA deepwater fields, and eventually gas from the KG-DWN-98/2 in 2019 8GAIL has now laid a counter-claim to do what is called a tie-in with the Odalarevu terminal from its regional KG Basin network on the ground that it is the nearest pipeline network. 8GITPL's tap-off point is 13 km away from Odalarevu whereas GITPL's is 50 km away. 8The ball in now in the court of the PNGRB Click on Reports for more
Details
The following are the latest updates on gas production by ONGC 8Daman has commenced production, C26 has been completed, both projects are contributing about 3-4mmscmd. 8Vasistha S1 has also commenced production (0.9mmscmd). 8ONGC expects Vasistha to be fully operational by November with an output of 5mmscmd. 8The output from the field is however set to decline after 2-3 years. 8KG-D6 production timelines have been maintained and ONGC foresees no delays in its earlier stated timelines. Drilling contracts have been finalized and rigs will be deployed by 8November. First gas by 2019 and oil by 2020. Click on Reports for more
Details
8Rs 1100 crore Phos acid expansion project: Tender for LSTK contractor this month 8Rs 25 crore GreenfieldSSP plant: On hold likely to be activated in December, 2017 8Rs 225 crore Phos acid expansion project: Tender in October, 2017 Click on Details for moreDetails
8Project Name: Greenfield hydroelectric plant Project Cost:: 4949 crore Project Description: Basic engineering activities are currently on for a 560 MW (4*140 MW) Kwar Hydroelectric Power Station at Kwar in Kishtwar district of Jammu and Kashmir. CVPP will float an RFQ for civil works for construction of Diversion Tunnel, Concrete Dam, Underground Power House and Tailrace Tunnels for which eequipmentrequired will be Rock Drill, Concrete Breaker, Asphalt Cutter, Grinder, Hydraulic Excavators, Dozers, Asphalt, Concrete, Composite, Bituminous Solutions, Stone Aggregates, Cement, DG sets, Piles, among others. The RFQ for hydro-mechanical and electromechanical equipment will be floated later. Hydromechanical equipment required will be penstock, head race tunnel, spillway, turbine, sluice gates, tailrace tunnel, among others. Project Event: RFQ for civil construction of Diversion Tunnels, Concrete Dam, Underground Powerhouse, Tailrace Tunnels is likely to be float in first week of August 2017. Click here for key contacts and other material information 8Project Name: Greenfield Hydroelectric Power Station Project Cost: Rs 826 crore Project Description: A 72 MW (3*24 MW) hydel power plant is coming up. EIA has been prepared and clearances are awaited. The company is expected to express requirement for 3 vertical Francis turbines shortly. However, it may also hire an EPC contractor. Major requirements: Construction of barrage and dam, cofferdam, powerhouse, steel lined penstock, turbines, generator, explosives, transmission lines, substation, crane, control equipment, desilting chamber, bays, tunnel construction, TBM (Tunnel Boring Machine) among others. Project Event: RFQ for 3 vertical Francis turbines expected in October 2017. Click here for more details
Details
8Revamp of Catalytic Reformer, Naphtha Hydrosulphurization units Project Cost: Rs 827 Project Description: Detailed engineering is currently on to convert the Catalytic Reformer unit to an Isomerization unit while also revamping the Naphtha Hydro-Desulfurization unit to a Naphtha Hydro-Treating unit to maximize isomerate yield and octane number and produce products like food grade hexane. Major Equipment Required: Feed pumps, Condensers, Separators, Heat-Exchangers, Strippers, Heater, Vessels, Filters etc. Project Event: RFQs for procuring long lead items are expected by mid-August, 2017. Expenditure Approval: Q2:2016 RFQ Date: Aug/2017 Release Date: Sep/2017 Completion Date: Q2:2020 Click here for full details 8Gasoline Hydrotreating greenfield unit Project Cost: Rs 554 crore Project Description: Engineering activities are on to install a new Gasoline Hydro-treating Unit (GTU) of 0.9 MMTPA capacity and associated facilities to produce 100% BS-VI MS. Environmental Clearance was granted by 20 March, 2017. Contracting for equipment and services are currently on. Major equipment required as of now are Heat-exchangers, Condensers, Feed Pumps and Valves. Project Event: RFQs for equipment will be expected by August, 2017. Expenditure Approval: Q1:2017 RFQ Date: Aug/2017 Release Date: Sep/2017 Completion Date: Q1:2019 Click here for full project, unit and facility parameters along with key contacts and their phone numbers.
Details
Project Cost: Rs 250 crore Project Description: A green field early production project would also involve the laying of a 8'' x 47 km pipeline. The proposed facilities in this project are HP Separator Skid, CO2 and Moisture Removal Skid, Dew Point Depression Skid, N2 Based Skid, Produced Water Storage and Bay Facilities and Other Utilities and Offsites. The equipment requirement will be Gas Turbine, Air Compressor, Storage tanks, Well Head, Water Injection Well, Flare Stack,Gas pipeline. Project Event: RFQs for the civil works can be expected by Q1, 2018. Expenditure Approval: Q2:2016 RFQ Date: Jan/2018 Release Date: Feb-March/2018 Start Date: Q2, 2018 Completion Date: Q3:2019 Click here for more, including capacity and key owner contacts, both at senior and operational levels
Details
For reference purposes the website carries here the following tenders: 8Ultrasonic thickness gauging of pipelines/ tankages at refinery Details 8Civil Works for preparation of cluster location for "MDDE" Site Details 8Civil works at drill site GKIT_H in Geleky area Details 8Carrying out Pipeline Work from HPCL Exchange Pit to BPCL Ennore Coastal Terminal Details 8Global Expression Of Interest for provision of Support Vessel for Acid Campaign at Ravva Block Details 8Global Expression Of Interest for Supply of Production Chemicals and Chemical Management Services in EOR Phase for Rajasthan Block Details 8Manufacturing, Testing, Inspection and Supply of Seamless Pipes for BS-IV ProjectDetails 8Supply of Ball Type On-Off Valves for VGO Unit for BS-IV Project Details 8Supply of Globe Control Valves for VGO Unit for BS-IV Project Details You can also click on Tenders for more For reference purposes the website carries here the following Newsclips: 8Soft crude prices to keep outlook for Indian upstream sector negative: Icra Details 8Iran urges decision on delayed IP Gas Pipeline Details 8Mamata Banerjee criticises Centre's decision to raise LPG prices Details 8GAIL under CCI scanner for breaching competition norms Details 8IOC’s new concept SAS to come back to company’s priority list Details 8Mamata Banerjee criticises Centre's decision to raise LPG prices Details 8GAIL under CCI scanner for breaching competition norms Details 8Infrastructure output grows 0.4 per cent year-on-year in June Details 8Japan's June oil sales fall to lowest for month in at least 29 years Details 8Pakistan interim PM-designate faces NAB inquiry over LNG contractDetails 8Negative outlook for domestic upstream petroleum companies: ICRA Details 8LPG prices to be hiked by Rs 4 per month as Centre pushes to end subsidiesDetails 8European oil producers' weak hedging shows bet on price reboundDetails 8Oil analysts more bearish as OPEC deal under scrutiny Details You can also click on Newsclips for moreDetails