NPK/SSP Annual Maintenance Project 
8Cost - Rs 0.28 Crore
8Project Description: A Fertilizer company is planning an annual shutdown maintenance in March or April 2018 at their existing fertilizer complex in India. The existing capacity is made up of 140000 MTPA of SSP, 45000 MTPA of Granular NPK mixed fertilizers, 40000 MTPA of Sulphuric acid respectively. Pre-Vendor Qualification may be necessary for a maintenance contractor.
8Project Event: RFQs for a maintenance contractor is likely to be released in January 2018.
Click here for more information
SSP/NPK Annual Maintenance Project
8Cost - Rs 0.20 Crore
8Project Description: A Fertilizer company is planning an annual maintenance shutdown in July or August 2018 at their existing fertilizer complex in India. The existing capacity is made up of 66000 MTPA of SSP, 60000 MTPA of NPK. Pre-Vendor Qualification may be necessary for a maintenance contractor.
8Project Event: RFQs for Annual Maintenance Contractor is likely to be released in March or April 2018
Click here for more information 
New Sulphuric acid unit: Equipment needed
An existing steel manufacturing company is planning to set up a greenfield Sulphuric acid unit with a capacity 125 MTPD in India.
8The project investment cost is around Rs 0.50 crore.
8The equipment requirements are Steam Turbine Generators, Economizers, Reheaters, Boilers, Sulphur Combustor, Drying Towers,  Vapor Separators,  Converters, Absorbers, Absorber Exchangers,  Sulphur filters, Sulphuric Melting Tank, Motors, Pumps and more
Click On Report for more
Captive Power Unit Expansion Project 

8Cost - Rs 224 Crore
8Project Description: A Fertilizer company is awaiting environmental clearance for an expansion of its captive power unit from 125 MW to 141 MW in India. The equipment requirements are Turbine Generator with their Auxiliaries and Utility, Boiler House including ESP, Ash Handling and other Auxiliaries, Fuel Handling plant, Automation, Instrumentation, Electrical Installations, Civil Work equipment and more
8Project Event: Tender for a Contractor is likely to be released in November 2017.
Click here for more information
Ammonia-Urea
 Annual Maintenance Project
8Cost - Rs 25 Crore
8Project Description: A Fertilizer company is planning an annual shutdown maintenance in June or July 2018 at their existing fertilizer complex at Kota in India. The existing capacity is made up of 650 MTPD of Ammonia, 1150 MTPD of urea. Pre-Vendor Qualification is necessary for a maintenance contractor.
8
Project Event: Tender for a maintenance contractor is likely to be released in February 2018.
 
Click here for more information
SSP Annual Maintenance Project   
8Cost - Rs 0.15 Crore
8Project Description: A Fertilizer company is planning an annual shutdown maintenance in April or May 2018 at their existing fertilizer complex in India. The existing capacity is made up of 67000 MTPA of SSP. Pre-Vendor Qualification may be necessary for a maintenance contractor.
8
Project Event: Tender for a maintenance contractor is likely to be released in January 2018.
Click here for more information Details
An existing company is planning to set up greenfield technical pesticide unit with a capacity 11775 MTPM in India.
8The project investment cost is around Rs 101 crore.
8The power requirement is about 7500 KVA, which will be sourced from Torrent Energy Ltd.
The requirement of raw materials are
8Coal- 100 MTPD
8High Speed Diesel- 190 Lit/hr
8Natural gas- 1000 SCM/hr 
Click on Report for more
  Details
For reference purposes the website carries here the following tenders:
8Procurement of GI Pipes for AOD Digboi Details
8Procurement of Lube Oil Pump For Digboi Refinery Details
8Supply of Chloride Guard for Mathura Refinari Details
8Supply of Tube Bundle for Panipat Refinery Details
You can also click on Tenders for more   
For reference purposes the website carries here the following Newsclips:  
8Oil payment, other issues with Iran resolved  Details
8Peak oil demand 'very real' as growth moves off road Details 
8LNG to account for around 40 pct of global gas trade by 2040 -GECF Details
8Oil prices firm as Iraq tensions escalate, shares extend rally  Details
8European indices surge lead by gains in oil stocks  Details
8Oil rises as tension escalates in Iraq's oil-rich Kirkuk Details
You can also click on Newsclips for more   
Details
8Project Name: Hydroelectric Greenfield Project
8Project Cost: Rs 6000 crore
8Project Description: The developer along with the consultant is carrying out the DPR activities for the environment clearance for a 680 MW (4*170 MW) greenfield hydel power project. TOR was accorded on 5 June 2014, and after its expiry, the TOR was extended on 26 May 2017. Three seasons baseline data for EIA report has been collected. Clearance from CWC, GSI and CSMRS has been obtained.The project is getting delayed due to heavy rains, as it makes the site inaccessible for long periods due to which investigation work was stalled several times. However, DPR has been submitted to CEA for techno-economic clearance. The SIA study for R&R plan is also ongoing. Environment Clearance is likely to be elicited by Q4 2018. The developer will come out with an EPC contract package.
8Project Event: RFQ for an EPC contractor is expected by Q1 2019.
8Expenditure Approval: Q3:2018
8RFQ Date: Q1:2019
8Release Date: Q2:2019
8Start Date: Q4:2019
8Completion Date: Q4:2025
Click here for more information
8Project Name: Combined Cycle Power Station-Maintenance
8Project Cost: Rs 11 Crores approximately
8Project Description: The owner is planning to conduct maintenance activities at its 1500 MW (4x216 MW GT and 2x253.6 MW ST) Combined Cycle Power Station. Unit-2 and Unit-4 (of 216 MW each) of the power plant will undergo maintenance and generator and combustion inspection, starting February 1st, 2018. RFQs for inspection and maintenance are expected to be rolled out in several packages.
8Project Event: RFQs for inspection and maintenance is expected to be rolled out in several packages by the end of November, 2017.
8Expenditure Approval: 2017
8RFQ Date: Nov/2017
8Release Date: Nov/2017
8Start Date: 1/Feb/2018
8Completion Date: 19/Mar/2018
Click here for more information
8Project Name: Thermal Power Station - Dismantling
8Project Cost: Rs 250 Crores approximately
8Project Description: The owner is planning to dismantle it's 135 MW (2x67.5 MW) coal based thermal power plant. Both units have been on reserve shut down (due to surplus power) since May, 2015. Technical details of the process are being discussed and are under finalization. RFQs for civil work and dismantling services of various equipment are expected by the end of 2017.
8Project Event: RFQ for dismantling services of various equipment is expected by Dec,2017.
8Expenditure Approval: Q2:2017
8RFQ Date: Dec/2017
8Release Date: Dec/2017
8Start Date: Q2:2018
8Completion Date: Q1:2019
Click here for more information
Details
8Project Name: PEL Block Exploratory Drilling
8Project Cost: Rs 150 Crore
8Project Description: Promoter is planning to drill exploratory wells in a PEL Block. Currently, the project is in preclearance phase. The environment clearance for the project is expected by January 2018. The 2D seismic survey for the block was carried out in the year 2015 for overall area of 185 sq km, out of which 154 sq km has been relinquished. Currently, exploratory drilling for 2 other wells is going on in the block. RFQs for the following equipment are expected shortly: Tanking Facilities, Casing, Cementing Facilities and Chemical Additives
8Project Event: RFQs for equipment and additives are expected by December 2017.
8Expenditure Approval: Q3/2016
8RFQ Date: Dec/2017
8Release Date: Jan/2018
8Start Date: Q2/2018
8Completion Date: Sep/2020
Click here for more details.
8Project Name: Ratnagiri Refinery Greenfield Project
8Project Cost: Rs 200000 Crore
8Project Description: An existing company is planning to construct a refinery in a joint venture of two companies with a capacity of 60 MMTPA. EIL has been hired as a consultant for preparing all documentation works. Land acquisition work is completed.
8Project Event: RFQ for different Technology Licensor will be released from December 2017.
8Expenditure Approval: Q1:2017
8RFQ Date: Dec/2018
8Release Date: Jan/2018
8Start Date: Q2:2018
8Completion Date: Q2:2023
Click here for more details.
8Project Name: Product Pipeline Greenfield Project
8Project Cost: Rs 2800 Crore
8Project Description: An existing company is planning to construct a product pipeline with a capacity of 4.5 MMTPA. Land acquisition for associated facilities had been completed.
8Project Event: RFQ for main-line along with pumping stations are expected by December 2017.
8Expenditure Approval: Q3:2015
8RFQ Date: Dec/2017
8Release Date: Jan/2018
8Start Date: Q2:2018
8Completion Date: Q2:2021
Click here for more details. Details
8Project Name: Hydropower Greenfield Project
8Project Cost: Rs 800 crore
8Project Description: The developer along with consultant is carrying out the site survey & investigation activities for scoping the environment clearance for a 84 MW (2*42 MW) greenfield hydel project on BOOT basis for a lease period of 40 years. TOR was accorded on 26 December 2011. The project is getting delayed due to rough surroundings at the site which is making survey work difficult. However, S&I works for three baseline season data is on the verge of completion and after that DPR work will be taken on. Environment Clearance is likely to be elicited by November 2018. The developer will come out with an RFQ for an EPC contractor after getting EC.
8Project Event: RFQ for an EPC contractor is expected by Q1 2019.
8Expenditure Approval: Q3:2018
8RFQ Date: Q1:2019
8Release Date: Q1:2019
8Start Date: Q3:2019
8Completion Date: Q4:2023
Click here for more information
8Project Name: Thermal Power Maintenance Project
8Project Cost: Rs 18 crore
8Project Description: The promoter has planned a 30-day scheduled maintenance of Unit-3 (210 MW) in the 1140 MW Thermal Power Station covering overhaul of the complete unit which includes overhauling of auxiliary parts of the turbine-generator sets, turbine bearings, air filters, nozzle, boiler tubes, valves, buckstays, chevron blades, generator relay, condenser tube banks, thrust bearing, journal bearings, pipes, turbine blades, turbine casing, HP, IP, LP turbine cylinders, rotor blades, fixed blades, among others.
8Project Event: RFQs for equipment required in the maintenance are expected by 1st week of November 2017.
8Expenditure Approval: Q2:2017
8RFQ Date: 7/Nov/2017
8Release Date: Dec/2017
8Start Date: 1/Jan/2018
8Completion Date: 30/Jan/2018
Click here for more information
8Project Name: Thermal Power Station - FGD Addition
8Project Cost: Rs 480 Crores approximately
8Project Description: The owner is planning the installation of an FGD unit and retrofitting of ESPs at it's 600 MW Thermal Power Station. At present the final stages of feasibility studies are ongoing. The installation is expected to begin by the end of December, 2019. RFQs for same are expected to be released in the second quarter of 2018.
8Project Event: RFQs for installation of FGD and retrofitting of ESPs are expected to be out by Q2, 2018.
8Expenditure Approval: 2016
8RFQ Date: Q2:2018
8Release Date: Q3:2018
8Start Date: Q4:Dec/2019
8Completion Date: Q3:2020
Click here for more information
8Project Name: Hydroelectric Power Station - Maintenance
8Project Cost: Rs 10 Crores approximately
8Project Description: The owner is set to begin maintenance activities at it's 815 MW (1x110 MW + 7x100.8 MW) hydroelectric power station. The owner has floated tenders for HVAC equipment which are currently under bidding and RFQ for electrical equipment are expected shortly. Subsequently, requirement for maintenance services and mechanical equipment are expected to follow.
8Project Event: RFQs for electrical equipment are expected in October, 2017.
8Expenditure Approval: 2017
8RFQ Date: Q4:Oct/2017
8Release Date: Q4:Nov/2017
8Start Date: Q4:2017
8Completion Date: Q1:2018
Click here for more information
8Project Name: Thermal Power Station - Maintenance
8Project Cost: Rs 9 Crores approximately
8Project Description: The owner is planning to carry out maintenance activities at its 62.5 MW RTS-B thermal power station. The activities are expected to begin by the middle of next month. RFQs for inspection, services and various short lead items and services are expected shortly.
8Project Event: RFQs for maintenance equipment and services are expected in October 2017.
8Expenditure Approval: 2017
8RFQ Date: Q4:Oct/2017
8Release Date: Q4:Nov/2017
8Start Date: Q4:2017
8Completion Date: Q1:2018
Click here for more information Details
8A surge in US LNG exports is always based on the assumption of higher worldwide demand for it. But what drives US exports would be the differentials of Henry Hub prices to Click on Report for more.

 8European and Asian gas prices, and whether the economic incentive exists to carry out the trade. The UK national balancing point (NBP) gas price – which serves as a proxy to the European traded gas price – remains at a premium to the US gas price (c.$6/mcf versus c.$3/mcf). Asian spot LNG prices fell sharply down to around $4.50/mcf at the start of 2016 but have since recovered to around $7-8/mcf. While this is a positive, the economics are still very tight. Find out more. Click on Report.
8Find out the real reasons why the shale gas revolution cannot be repeated in other parts of the world even where large reserves have been found. Click on Report for more.
8Find out more on what is the oil price that the Saudi Arabia is looking at. Also why the Saudis have more patience and a longer time horizon than other oil producers in the world. And how the OPEC still has the power to impose a floor price to global oil. Click on Report for more.
8Find out more on how Great Eastern Shipping Company put together a senior loan facility for four of its jackup rigs. Click on Report for more.
8Find out more on how the IMO's decision to postpone the new Ballast Water Treatment norms has put off the phasing out of many large ships by at couple of more years. Click on Report for more.
8Comparative Analysis of Barite and Hematite Used in Water-Based Drilling Fluid shows that one of the two has a distinctive advantage.Click on Report for more.
8Find out more on how crowdsourcing is used as a channel to solicit innovative ideas to reduce the environmental footprint of oil and gas exploration, development and production. The results have come as a surprise. Click on Report for more.
8There are many new high-tech proppants in use in the market today, and it is time Indian companies think of using them. Click on Report for more.
8The global oil & gas pipeline industry is set to grow rapidly by 2019. Having ensured that the Indian market remains under their grip now that a domestic value added caveat has been put in place, it is time for domestic pipe manufacturers to go out and compete for the spurt in global orders. But will they?. Click on Report for more.
8Indian energy sector reforms: An insight. Click on Report for more.
8Reliance Defence and Engineering Limited has delivered another 73,500 DWT new-built Ice-class Panamax Bulk Carrier for an international client using best-in-class technology. Click on Report for more.
8Indian threats of curtailing Iranian imports are not borne by crude import figures. Find out why. Click on Report for more.
8KG-D6 gas production is at an all time low of 5.4 MMSCMD while CBM output is at 0.6 MMSCMD. Click on Report for more.
8The government is selling 100% of Helicopter carrier Pawan Hans and 100% of its stake in the fertilizer consultancy company, PDIL. Get the offer documents here. Click on Report for more.
8A series of mid-term MOU evaluation meetings are currently on between the government and public sector oil companies. Click on Report for more.
8Chinese crude and gas imports are rising rapidly, fueling suspicion that its economy is reviving faster than was thought earlier. This will have big implications on prices. Chinese imports are offsetting a rise in shale output from the US. This bullish sentiment however is tempered by other reports that there will be a supply surge in 2018 and despite the Chinese surge, global demand will be lower than earlier estimated. In the face of conflicting claims, it has become difficult to figure out which way the markets are going to behave.Click on Report for more.
8The new Saudi Aramco office in India will strive toward qualifying more vendors in equipment and services as well as raw materials needed by the company for its many projects. The website carries here an interview with Saudi Aramco president and CEO Amin Nasser. Click on Report for more.
8A new way to mitigating future elemental sulfur and even removing its deposition tenfold by using a cheaper solid-liquid mixture -- simple garlic and low-grade heavy diesel oil -- has been found. Click on Report for more.
8Find out more on the kind of energy efficiency projects that are getting funded in India. Click on Report for more.

Details
The Mozambique LNG project, where ONGC, OIL and BPCL are heavily invested, seems to be gaining traction.
Advisors are working on the following aspects as of now:
8EPC arrangements
8Possibility of procurement of LNG fleet
8Long term LNG sale and purchase agreements
Click on Reports for more Details
Find out more on how oil and gas equipment suppliers are saving up to 60% in product development time by use of new stimulation technology.
8Indian equipment companies stand to benefit too from the use of such technologies.
8Stimulation reduces the need for more prototypes and it improves system capability.
8Find out more on which are the best companies in the world that can radically change the way organizations design products and make decisions.
8And then which are the companies which do the best stimulation work in the world.
Click on Reports for more Details
The gas market is India continues to remain badly under-analyzed.
8The price differentials between all types of substitutable fuels and LNG as well as domestic gas remain not well understood.
8Fuel switching between LNG, ethane and LNG, or between dirty fuels such as petroleum coke and LNG is a phenomenon that gas suppliers do not adequate attention to.
8The dynamics are not well understood yet as the information flow on how these differentials work at the retail level is non-transparent.
8This in turn forces gas suppliers to look at governmental intervention, from tax cuts to subsidies, as the sole way to spur demand.
8In India too, like the way it is globally,  price differentials are the major determinants of demand at the supply level. While Henry Hub prices are not directly linked to crude price, with the oil/gas price ratio ($ per bbl WTI/$ per mcf Henry Hub) of around 17x at the end of September which is well outside the long-term ratio of 6-9x, they are circumscribed by the prices of heating oil and coal prices.
8But no one really understands these differentials well enough in India
Click on Reports for more Details
For reference purposes the website carries here the following tenders:
8Supply, Installation and Commissioning MOV Actuators at NRPL, Mathura  Details
8Supply of Chlorine By Setting Up a Chlor Alkali Plant  Details
8Supply of Centrifugal Pump Numaligarh Refinary  Details
8Supply of Alkyl Aryl Phosphate Easter Durad 220 IOC St 4558 Details
8Supply of 36 MT of Diethyl Aluminium Ethoxide at IOCL Panipat Refinery  Details
8NationalReconciliationProcessIB09102017  Details
8Contract for Movement of Polymer from PWH to PTA Terminal  Details
You can also click on Tenders for more   
For reference purposes the website carries here the following Newsclips:  
8IOC Dropped Plans to Merge Chennai Petroleum Holding 51.89% Push State Exit of NIOC 15.40%  Details
8Iraq Gas Exports Q-3 of 2017 Reached 125.2 MMT and 255.11 MMT of Condensates or 46 Over 22 Shipments Details 
8You Could Be Soon Buying Petrol Online. Read What Experts Say Details
8Russia Reaches Outline Debt Restructuring Agreement With Venezuela -RIA  Details
8Reliance Industries Exits From Overseas Oil and Gas blocks Details
8Vedanta Chairman Anil Agarwal Not to Seek Board Position on Anglo Details
8 Energy Giant Saudi Aramco Denies Reports Shelving International Listing Details
8South Korea's Sept Iranian Crude Oil Imports Rise to 6-Month High  Details
8Feasible to sell petrol via e-commerce, but safety needs priority: Experts Details
You can also click on Newsclips for more   
Details
8Project Name: Gas based Power Plant
8Project Cost: Rs 100 Crore
8Project Description: Promoter is planning development of a gas based 25 MW thermal power plant. The project involves addition of capacity to an existing unused 5 MW capacity turbine. The existing turbine has a provision of increasing the capacity beyond 5 MW. Currently, the project is in pre-planning stage. The company is looking for technology provider in order to support the project. Moreover, the consultant for the project is also expected to be hired soon. RFQ for gas based engine are expected soon.
8Project Event: RFQ for hiring the consultant for the project is expected by Q1 2018.
RFQ for equipment is expected by Q2 2018.
8Expenditure Approval: Q1/2018
8RFQ Date: Q1/2018
8Release Date: Jan/2018
8Start Date: Q2/2018
8Completion Date: Sep/2020
Click here for more details.
8Project Name: Greenfield Pipeline Project 
8Project Cost: Rs 1330 Crore
8Project Description: An existing company along with EPC contractor is carrying out construction work to install an LPG pipeline of 10.75" OD, with a length of 673 KM.
8Project Event: RFQ for commissioning and pre-commissioning activities is expected by November 2017.
8Expenditure Approval : Q3:2014
8RFQ Date : Nov/2017
8Release Date: Dec/2017
8Start Date : Q1:2015
8Completion Date : Q1:2018
Click here for more details. Details
8Project Name: Greenfield Multipurpose Project
8Project Cost: Rs 1500 crore
8Project Description: The developer along with PFR consultant is carrying out the site survey & investigation activities for scoping the environment clearance for a 300 MW (3*100 MW) greenfield multipurpose project. TOR was accorded on 25 January 2017. At present, PFR prepared, and has been submitted to CWC for appraisal and site survey activities are currently on. The developer will come out with an EIA consultant tender soon and after the EC is elicited, package wise contracts would come.
8Project Event: RFQ for an EIA consultant for preparation of DPR and EIA/EMP report is expected by Q1 2018.
8Expenditure Approval: Q4:2017
8RFQ Date: Q1:2018
8Release Date: Q1:2018
8Start Date: Q2:2019
8Completion Date: Q3:2024
Click here for more information
8Project Name: Greenfield Hydroelectric Project
8Project Cost: Rs 680 Crores approximately
8Project Description: The developer is planning to construct a 67 MW (3*22.33 MW) Hydroelectric Project. The project is under advanced stages of DPR preparation and the owner is likely to float the RFQ for an EPC contractor by the first quarter of 2019.
8Project Event: RFQ for an EPC contractor is expected by the first quarter of 2019.
8Expenditure Approval: 2014
8RFQ Date: Q1:2019
8Release Date: Q3:2019
8Start Date: Q4:2019
8Completion Date: 2024
Click here for more information
8Project Name: Greenfield Hydroelectric Project
8Project Cost: Rs 650 Crores approximately
8Project Description: The developer is planning to construct a 66 MW (3*22 MW) Hydroelectric Project. The project has obtained EC and the owner is currently accepting RFQs for the signing of PPAs. Also, RFQ for civil work and BoP is expected to be out shortly.
8Project Event: RFQ for signing of PPA is currently being accepted by the proponent and RFQs for civil work and BoP are expected to be out by second the quarter of 2018.
8Expenditure Approval: 2014
8RFQ Date: Q2:2018
8Release Date: Q4:2018
8Start Date: Q1:2019
8Completion Date: 2024
Click here for more information
Details
8India coal imports have been falling in the last few years but they are likely to swing upwards from 2019. Find out why. Click on Report for more.
8Australian will find it increasingly difficult to sign long term LNG contracts with India but the Indian spot market holds opportunities and find out why. Click on Report for more.
8Saudi Arabia has declared that it will curb November crude oil exports by 7% or 560,000 barrels but as prices rise, US shale producers are ramping up supplies. Click on Report for more.
8A new business development opportunity is coming up in a multi-product Rs 1500 crore pipeline project in India. Click on Report for more.
8Will renewable energy based cooking replace LPG in India? Take part in a discussion on the topic. Click on Report for more.
8A new 1800 crore production pipeline extension is coming up with additional pumping stations in India. Click on Report for more.
8Find out more on an Indian market leader on Bio-ethanol facilities, Brewery plants, Water & Wastewater treatment systems, Critical Process Equipment & Systems, Hipurity solutions and Bio-products. Click on Report for more.
8Take a workshop to under the basic concept of Risk-Based Inspection and the basis for the API 580 RBI program and its methodology. Click on Report for more.
8India in the context of International Maritime law and arbitration. Learn more. Click on Report.
8Intense subsidy-based coal to gas switching in China that has lead to a surge in demand for LNG is coming to an end and this will have serious implications for the global LNG market. Then again, gas-to-power and transport have been touted as potential growth drivers for gas demand in China, but gas-fired power generation is still hobbled by weak economics.Click on Report for more.
8While gas based power projects are not viable in India, they seem to be in Pakistan. China Machinery Engineering Corp. signed an agreement on Friday with the government of Pakistan’s Punjab province to build a 1.26 GW gas-fired power plant in the city of Jhang. What kind of economics is driving gas based power projects n China?Click on Report for more.
8If you are looking for LNG solutions, including setting up terminals in India, here is an international LNG portfolio company that you must get in touch with. Click on Report for more. Details
For Indian LNG suppliers who are willing to tap the transport sector, the website carries here a detailed outline of natural gas engines run on LNG
Details are given of advances in:
-- High Pressure Direct Injection engine technology
-- High Efficiency Spark Ignited engine technology
-- Fuel storage and delivery solutions
8How do you then go about building an entire infrastructure around it?
Click on Reports for more Details
An Indian origin promoter is pushing a new form of what are called Microcell Carbon Foam Batteries for Grid Scale Renewable Energy Storage Systems
8Installations have been put up in Japan and their performance has been far superior to conventional batteries.
8These system can be a great way of handling power needs in non-grid oil & gas locations and are going to cheaper than conventional diesel led solutions.
Click on Reports for more Details
A gigantic Japanese gas buyer has massive global expansion plans across the entire LNG value chain
8It intends to become an international buyer, supplier and trader and is willing to go deeper into foreign markets through strategic investments.
8The company is already working with Bangladesh
8It is time for intrepid Indian entrepreneurs to coax the Japanese giant to come to India, perhaps into LNG terminals, transmission pipelines and the city gas business
Click on Reports to know more Details
The public sector Cochin Shipyard Ltd's core competency is shipbuilding and ship repairing.
8Repairing, however, is twice as profitable as building new ships and so the company is trying to shift its business mix
8It has  a big order book and it has an L-1 status on another Rs 5400 crore of orders
8Enhanced oil & gas offshore activity is expected to be a big opportunity for the shipyard
Click on Reports to know more on the company Details
A poll of global oil & gas CEOs shows that as many as 82% of them see their company growing in the next one year.
8The figure goes up to more than 90% when a three-year span is taken into account
8Find out more on which are the segments they see more growth coming from
Click on Reports Details
US shale gas production reached 73.84 Bcf on September 5, passing the prior daily record set in February 2016.
8With a 130 percent increase in the US rig count since August and new takeaway infrastructure capacity coming online through the end of 2017 and into 2018, the possibility for new record levels of gas production in the coming months may be likely.
8The 30-cent spread between October and January gas futures - which is about 15 cents narrower than the same time last year -  may hint at a gas market that traders perceive to be well supplied.
8These factors point to lower Henry Hub prices in the coming months.
Click on Reports for more Details
For reference purposes the website carries here the following tenders:
8Supply of Pump Spares at IOCL Guwahati Refinery Details
8Supply of Pipes to Mathura Refinery Details
8Supply of Pipe Fitting at IOCL Paradip Refinery Details
8Supply of Liquid Nitrogen in Gujarat Refinery Details
8Rate contract of laying and maintenance of underground carbon steel pipe lines in various fields of Mehsana  Details
8Procurement of 5400 MT of Sodium Chloride for entering into RC for two years (ONGC)  Details
8HPCL Tender for Desalter Internals for 11-V-02 Details
8Annual Rate Contract for Supply of N2 Gas Cylinders for NGRL Details
You can also click on Tenders for more   
For reference purposes the website carries here the following Newsclips:  
8Renewables to account for 40 per cent of India’s energy mix by 2030: Power Minister R K Singh Details
8Shell buys electric vehicle charging firm New Motion Details 
8Aker BP wins approval for gas lift at Tambar oilfield Details
8Oil prices fall on higher U.S. crude inventories Details
8China's crude oil buying spree looks set to continue: IEA Details
8ONGC may sell IOC stake to LIC in block deal to fund HPCL acquisition Details
8 Import of oil-drilling rigs kept out of GST purview Details
8L&T plans to bid for more ONGC work after Daman win Details
8Aramco to invest $300-b in India in next 10 years and in biggest upcoming oil refinery in Ratnagiri, Maharashtra Details
You can also click on Newsclips for more   
Details
8Project Name: Greenfield Hydroelectric Project
8Project Cost: Rs 200 Crores approximately
8Project Description: The owner is planning to set up a 26 MW (2*13 MW) hydel plant. The PFR has been prepared and survey and investigation (S&I) is ongoing for preparation of DPR. RFQ for drilling is expected shortly and RFQ for major civil work is expected to be out in 2019.
8Project Event: RFQ for drilling for survey & investigations is expected to be out by Q1, 2018.
8Expenditure Approval: 2012
8RFQ Date: Q1:2018
8Release Date: Q2:2018
8Start Date: 2019
8Completion Date: 2023
Click here for more information
8Project Name: Gas Power Station Maintenance Project
8Project Cost: Rs 14 crore
8Project Description: The owner has planned a 5-days scheduled maintenance of Unit-2 (137.76 MW) in the 430 MW Gas Based Power Station covering major inspection (type C) of equipment which includes overhauling of auxiliary parts of the gas turbine set, compressor parts, complete hot gas path inspection and generator rewinding and minor inspection of the air fuel ratio (AFR).
8Project Event: RFQ of equipment required in maintenance are expected by fourth week of October 2017.
8Expenditure Approval: Q2:2017
8RFQ Date: 27/Oct/2017
8Release Date: Nov/2017
8Start Date: 1/Jan/2018
8Completion Date: 5/Jan/2018
Click here for more information

8Project Name: Thermal Power Plant - FGD Addition
8Project Cost: Rs 600 Crores approximately
8Project Description: The owner is scheduled to install FGD (Flue Gas Desulphurisation) units and upgrade ESPs (Electrostatic Precipitators) at its 920 MW (2*210 MW + 2*250 MW) thermal power plant. At present, the DPR is being prepared along with the consultant and preparation of tender documents are expected to follow. The project is expected to kick off in early 2021. Commercially, RFQs for FGD installation and retrofitting of ESPs are expected to be out by the second quarter of 2018. Interested parties can get in touch with project promoters for pre qualification and other related activities. Already two Chinese companies have approached the promoters. 
8Project Event: RFQs for FGDs and retrofitting of ESPs are expected to be out by Q2, 2018.
8Expenditure Approval: 2016
8RFQ Date: Q2:2018
8Release Date: 2018
8Start Date: Q1:2021
8Completion Date: Q4:2021
Click here for more information
8Project Name: Thermal Power Plant - Maintenance
8Project Cost: Rs 15 Crores approximately
8Project Description: The owner is expected to conduct capital overhaul in Unit-6 and Unit-7 of its 920 MW (2*210 MW + 2*250 MW) thermal power plant. RFQs for same are expected to be out in early 2018 and the owner is likely to engage an EPC contractor. 
8Project Event: RFQ for capital overhaul and maintenance is expected to be out in Q1, 2018
8Expenditure Approval: 2017
8RFQ Date: Q1:2018
8Release Date: Q2:2018
8Start Date: Q3:2018
8Completion Date: Q4:2018
Click here for more information
8Project Name: Greenfield Hydroelectric Project
8Project Cost: Rs 1800 crore
8Project Description: The owner along with consultant is writing out the detailed project report for scoping the environment clearance for a 252 MW (4*63 MW) greenfield hydel project. TOR was accorded on 4th March 2014 which would be valid for four years. Survey and investigation activities for updated baseline data for three working seasons has been completed and EIA/EMP activities are in progress. Socio-economic survey, land survey, and public hearing are getting delayed due to heavy rains in the project area and would be completed in the next 7-8 months. The developer will come out first with major civil works, and HM and EM works subsequently after a month's gap each after procuring EC.
8Project Event: RFQ for civil works are expected by 3rd Quarter of 2018.
8Expenditure Approval: Q1:2018
8RFQ Date: Q3:2018
8Release Date: Q3:2018
8Start Date: Q1:2019
8Completion Date: Q3:2024
Click here for more information
Details
The global oil & gas markets have become more volatile and consequently demand-supply and price projections are also changing every quarter.
8For some, this is the season to be bullish on the oil & gas sector, particularly LNG.
8The current thinking is that new LNG supply in 2016 and 2017 is being absorbed by the market and LNG is not in oversupply. This is reportedly evident from the fact that LNG spot prices are up in 2017, breaking a two year trend.
8Then again, European storage is viewed as the dumping ground for any surplus LNG cargos but fresh data shows that storage withdrawals have been higher, implying there is no excess LNG in the market.
8Floating Storage Regasification Units have moved beyond small new country markets and into expanding bigger demand markets, such as Pakistan and Bangladesh. thereby enlarging the market for LNG.
8The big changer is the increased demand for gas from China which plans to increase natural gas to 10% of its energy mix.
8If demand indeed catches up with supply, the price of LNG is likely to remain high and this will have implications for the power sector.
Click on Reports to download a lot of data on the subject Details
Latest projections are now showing that gas based power plants can only be viable with an adequate carbon tax on emissions.
8The levelized tariffs of high efficiency gas turbines in Asia can match coal based power but only with a hefty carbon tax.
8But even with such a tax, if the current global demand-supply gap evaporates, the landed price of LNG is likely to shoot up, making gas-fired power unviable.
8The government is now thinking of bundling gas based generation with renewable power, as was evident from the Petroleum Minister speech at the CERA conference this week.
8But for that to be viable, concerted government action will be needed. 
8Will that happen?
Click on Reports for more  Details
What is the latest government figure for investment in the Indian oil & gas sector over the next four to five years without including midstream investments?
8The figure comes to $ 73 billion.
8This is a large number by any yardstick and will come as sweet news for equipment and service suppliers.
Click on Reports to get a breakdown of this figure Details
With the government having decided, at least for now, not to coerce its oil and gas companies to take on the burden of under recoveries, their fortunes seems to be up.
8Refinery GRMs are likely to flare up in Q2 and the subsequent quarters on the back of higher GRMs posted by Singapore refineries and inventory gains on account of higher crude prices.
8GRMs are expected to be in the range of $ 9-$9.5 hereon, with the exception of MRPL, while RIL is projected to show a $ 12.6/bbl margin.
8Public sector oil marketing companies margins' on auto fuels are up.
8Similarly, ONGC is likely to score higher on account of a likely uptick in oil production after years of stagnation and a 10-15% annual increase in gas output over the next five years.
Click on Reports for more Details
The bet is that LNG volumes will grow at double digits for the rest of the year
8While LNG imports grew by 16% in FY17, they declined by 4% YoY during April-August 2017
8Lower production from RIL's D-6 block and a possible delay in the gas production from Daman until after 2018 monsoons may see LNG uptake remaining strong next year too.
8But a lot would however depend on how LNG prices behave. Higher prices will make alternative fuels more attractive.
Click on Reports for more Details
Even though the key oil and gas players seem to have heaved a sigh of relief with the government's decision to keep the burden of under recoveries away, the danger is not over yet.
8The room for further fiscal maneuvering is not there and any further hike in crude prices will push this government towards price control.
8The Modi regime is acutely image centric and it is currently under pressure from all directions. If push comes to shove, it will capitulate easily.
8This regime is text book oriented in its policies, influenced by the presentations given by assorted bureaucrats and Niti Ayog economists, whereas the earlier government, headed by an economist, was more centered around the politics of its economics.
8But that aside, those who want to bet on the oil companies, be prepared to face an uncertain future. For now.
Click on Reports for more Details
For reference purposes, the website carries here the following data:
8Singapore GRM projections, with GRM increases lead by higher gasoline and diesel cracks
8Relative performance of oil & gas indices with respect to the Sensex
8Polymer spreads in India over time
8Petrol/diesel price differentials
8Possible LNG volumes in relation to domestic gas output
8Expected RIL GRM
Click on Reports for more Details
Find out more on the key operating parameters of a low cost LNG supplier who is present right up the value chain.
8The focus seems to be on low onland extraction costs of between $ 0.5-2/mmbtu, $ 1-2/mmbtu liquefaction cost, $ 0.5-3/mmbtu DES Asia transportation cost, regasification cost of $ 0.5/mmbtu and marketing costs of between $ 0.2-0.4 for B2B and $ 1.5 to 2.5 for B2C transactions. Trading costs are pegged at $ 0.2-04/mmbtu
8Clearly liquefaction costs are coming down and there is already a 60% differential between onshore and FSRU costs.
8These are the new benchmarks.
Click on Reports for more Details
With the majority of second-hand tonnage transactions taking place in the dry bulk sector it’s easy to lose sight of what is happening over at the tanker side and for a good reason. Things have been mostly quiet for the last seven months with the exception of short periods of increased activity during the summer months.
8The tanker market has evolved into a market that requires fast reflexes. Cycles are becoming shorter, usually lasting 16 to 18 months, thus creating a sense of uncertainty as far as when to off load a respective asset or invest in tonnage.
8Taking into consideration that tankers assets are depreciated differently compared to bulkers and how oil majors can influence trends as far as buying, selling and contracting tonnage, it is very common to witness price iregularities on the transactions within the same time period.
8Electric cars, MGO regulations, developing economies, clean and renewable energy policies and last but not least the “Paris climate Accord”, all play a part on the everlasting and ongoing discussion of what the influence on tanker demand and supply will be.
Click on Reports for more Details
The website carries here a comparison of landed prices in India of RasGas contracts, which are indexed to crude prices, and GAIL's Henry Hub indexed volumes under different sensitivities.
8GAIL has booked 86% of its contracted 2018-19 US LNG volumes. Find out more about where they have been placed. A large quantum of this has been placed on an Indian bulk buyer. Yet, the Indian volumes will face a price disadvantage.
8What are the projections on gas transmission volume growth in India over the last three years? Find out more
8What will be the impact of uniform tariff on key gas transmission companies in India
8Find out more on how GAIL plans to corner around 9 mmscmd of gas supply contracts coming up from new fertilizer plants
Click on Reports for more Details
8ONGC Videsh has lined up to take a briefing on how to bid for the massive Azadegan field in Iran. There will be yet another big Iranian that OVL plans to bid for. Meanwhile even as OVL struggles to find its moorings in Iran, the Chinese have already begun delivering oil from Iran. Click on Reports for more.
8The Draft National Energy Policy has not taken into account the full impact of the disruptive technology in its calculations. Click on Reports to find out more
8Download a full presentation on the Indian oil & gas sector by a senior petroleum ministry bureaucrat. Priorities are spelt out. Click on Reports.
8Find out more on a smart logistics conference promoted by a state government. Click on Reports for more.
8A weak environment has slowed down L&T order book growth but that is only a temporary blip. Find out how things are going to look bright sooner than later for the company. Click on Reports for more
8Coal India Ltd's performance has been impacted on many counts, such as grade slippage, e-auction price decline, deceleration in volume growth and uncertainties around the wage hike. over the last two years but the future is brighter. Click on Reports for more.
8Petronet LNG: Expect 40 percent capacity utilisation of Kochi terminal in 2018. Click on Reports for more.
8Find out more on the latest IMF projections on how oil prices are going to behave in 2018. Do not expect much change is what it seems to be saying. Click on Reports for more.
8Find out more on the growth potential of the Indian machine tools and welding industry.Click on Reports for more.
8India coal stocks are at rock bottom  and this is good news for bulkers. Click on Report for more.
8Find out more on the methodology and specifications that go into determining the LNG benchmark price for India. Click on Report for more.
8L&T Hydrocarbon Engineering wins a Rs 1150 Cr contract for the Daman platform installation and associated pipeline project but will ONGC be able to stick to the pre 2018 monsoon deadline for first gas? Click on Reports for more.
8As the Indian oil & gas sector grows, so does Pakistan's. Massive earnings growth is expected from its companies. And notwithstanding large capex cuts globally, Pak E&Ps are setting out to ramp up exploration on the back of lower onland cost of production. Click on Report for more.
8Find out more on how much more EIL earns from its big ticket projects in relation to smaller sized consultancies. What is the PMC margin in big refinery projects?Click on Report for more
8Is the government thinking of approving a minimum economy of scale output from refineries with petrochemical projects so as to keep them viable in the long run? Click on Report for more.
8Get a full database on existing, under construction, planned and proposed LNG terminals in India along with spatial display of terminals and gas pipelines in India. Click on Report for more.
8Find out more on new business opportunities planned by Petronet LNG Ltd. Click on Report for more. Details
8Project Name: Onshore Field Development
8Project Description: Promoter is planning the development of an oil field in the Cambay Basin, Gujarat. The block, along with two other blocks had been awarded to the company in small fields bid round 2016. The company is planning a study of the oil field prior to start production from the oil field. The project involves detailed energy studies of the oil field to estimate possible reserves and production.
Further RFQ for the project is expected shortly.
8Project Event: RFQ for hiring consultant for oil field studies and analysis is expected by November 2017.
8Expenditure Approval: Q3/2017
8RFQ Date: Nov/2017
8Release Date: Dec/2017
8Start Date: Apr/2018
8Completion Date: Apr/2019
Click here for details
8An oil & gas company has proposed developmental drilling of 3 wells for incremental production of crude oil. The project has been listed out as an expansion project for already existing 20 well development drilling going on in the existing facility. Currently, the pipeline package tendering for the project is going on. Meanwhile, the rigs for the project have also been finalized. RFQs for the following equipment namely Coupling, Xmas Tree, Tanking Facilities, Safety Valves etc are expected shortly. Meanwhile, the mobilization contract for the project has also been signed.
Click here to go to our software for key contacts for this RFQ prospec
Details
Ammonia-Urea & Captive Power Unit Greenfield Project
8Cost - Rs 7000 Crore
8Project Description: A Fertilizer company is awaiting environmental clearance for its greenfield ammonia-urea unit with a capacity of 2x2500 MTPD of ammonia, 4000 MTPD of urea and 2x 150 MW of Captive power unit in India. The plant will be attached to a FRSU based terminal.
8
Project Event: RFQs for LSTK contractor is likely to be released in 2018.
Click here for more information
DAP/NPK- Phosphoric Acid & Sulphuric Acid Greenfield Project
8Cost - Rs 2000 Crore
8Project Description: A Fertilizer company is awaiting environmental clearance for its greenfield DAP/NPK unit with a capacity of 6000 MTPD of DAP/NPK, 3000 MTPD of Phosphoric Acid and 4500 MTPD of Sulphuric Acid Unit in India.
8
Project Event: RFQs for LSTK contractor is likely to be released in 2018
Click here for more information
Single/Triple & Phosphoric Acid Greenfield Project   
 8Cost - Rs 40 Crore
 8Project Description: A Fertilizer company is awaiting environmental clearance for its greenfield Super Phosphate Unit with a capacity 100000 MTPA of Single Super Phosphate, 60000 MTPA of Triple Super Phosphate and 30000 MTPA of Phosphoric acid in India.
8
Project Event: RFQs for a contractor is likely to be released in 2018
Click here for more information   Details
Energy Saving-cum- Ammonia-Urea Expansion Project

8Cost - Rs 540 Crore
8Project Description: A Fertilizer company has hired EPC contractor, which is conducting detailed engineering for the energy saving-cum-expansion project which will reduce energy consumption of urea from 6.5 Gcal/t to 5.75 Gca//t, ammonia from 9.6 Gcal/ ton to 8 Gcal /ton while enhancing ammonia capacity from 240900 MTPA to 328500 MTPA, urea from 419750 MTPA to 569400 MTPA in India. The project currently awaits environment clearance. The contractor will begin taking out RFQs for equipment shortly.
8
Project Event: RFQs for equipment are likely to be released in November or December in place of October 2017 due to delay in the conduct of detailed engineering studies.
Click here for more information
Super Phosphate-Sulphuric Acid & NPK Fertilizer Expansion Project 
8Cost - Rs 75 Crore
8Project Description: A Fertilizer company is planning is awaiting environmental clearance the expansion of its Super Phosphate capacity from 140000 TPA to 580000 TPA, Granulated NPK Fertilizer from 45000 TPA to 440,000 TPA and Sulphuric acid from 40000 TPA to 140000 TPA in India.
8
Project Event: RFQ for a contractor is likely to be released in November or December in place of October 2017 due to a delay in environmental clearance.
Click here for more information
Ammonia-Urea Annual Shutdown Maintenance Project 
8Cost - Rs 30 Crore
8Project Description: A Fertilizer company is planning an annual shutdown maintenance in July or August 2018 at their existing fertilizer complex in India. The existing capacity is made up of 1520 MTPD of Ammonia, 2610 MTPD of Urea and 51 MW of Captive Power. Pre-Vendor Qualification is necessary for a maintenance contractor.
8
Project Event: Tender for a maintenance contractor is likely to be released in January 2018
Click here for more information   Details Details
For reference purposes the website carries here the following tenders:
8Supply of remote seal type DP transmitter at IOCL Paradip refinery Details
8Supply of hydro test pump at IOCL Paradip refinery Details
8Supply of hydraulic filters for barauni refinery Details
8Supply of GC calibration standard at digboi refinery Details
8Procurement of pump spares for Paradip Refinery Details
8
Hiring of Security Services for GSPC across Gujarat Details
You can also click on Tenders for more 
 
 
For reference purposes the website carries here the following Newsclips:  
8 Pradhan challenges oil and gas industry to find a ‘Super Basin’ in North-East Details
8GST council recommends rates for offshore exploration, services and transportation of natural gas  Details 
8China's top coke producer Shanxi to curb output in pollution war  Details
8Oil Minister Pradhan launches prepaid smart cards for CNG consumers Details
8Cabinet clears pact with Japan for setting up flexible LNG market  Details
8Petrol pump dealers call off October 13 strike Details
8L&T Hydrocarbon Engg bags Rs 1,150-cr mandate from ONGC Details
8GSFC in focus post huge rally in holding companies Details
8scientists solving for sulphur Details
You can also click on Newsclips for more
Details
In the last season, projections were that the LNG over supply situation will continue till 2025
8This season, the projections are that demand will match supply by 2021-22.
8Such a development can be nothing but bad news for the gas-based power sector. If LNG prices move up, the price of LNG dependent gas based power will go even higher in the merit order power market in India, making it that much more difficult to get the current stranded capacity restarted. The fact that coal based power plants can be retrofitted to act as low base load and peaking stations is a detriment already but higher price of gas will kill the hope for a revival of stranded gas based power projects in the country.
8The shifts in projections are triggered through a subtle release of data led by the biggest LNG suppliers in the world, and among them are Shell, Exxon-Mobil, BP and Total.
8Research agencies crunch the fresh data and then help bring about a change in sentiment.
8BP, for example, has an inordinate amount of clout with Cambridge Energy Research Associates (CERA), one of the world's best recognized research outfits in the oil & gas sector, based out of Oxford, not far from BP's headquarters. CERA works with IHS, the world's largest consulting company, and the two together form a formidable "intellectual force" and a dissemination point that triggers off a chain of supporting reports which eventually impacts sentiments, policies and prices.
8Some years ago, CERA was funded by BP to bring out a report on the Indian oil & gas sector wherein it drew up a road map of how big investments can make India nearly self sufficient in gas. The story, however, turned out to be different. While investments are pumped into the KG Basin, there aren't enough reserves, unlike what CERA had projected, to absorb funds beyond a point. 
8The usual modus operandi of Big Research is to push a lot of information upfront to dazzle the audience. No one does the assessment of all they said a year later when the ground reality is different.  For then it is time for another set of new data points to emerge. The razzle-dazzle continues in what is a seemingly unending cycle.
8Big bang events like the one hosted in India by CERA this week is nothing but a lot of razzmatazz put together by Big Oil, Big Research and Big Government.
8The oil and gas sector is, sometimes, full of sound and fury, signifying nothing.
Click on Reports for more  Details
For reference purposes the website carries here the following tenders:
8Procurement of OFC based Pipeline Condition Monitoring and Surveillance System for Kota-Jobner Pipeline Details
8Procurement of OFC based Pipeline Condition Monitoring and Surveillance System for Mumbai-Uran Pipeline Details
8Fabrication of 475 KL ATF Tanks along with Pipeline and Civil jobs Details
8Supply of Pipes and Seamless Pipes on ARC basis Details
8Supply of Pipeline Locators to PHBPL Haldia station for tracing underground hydrocarbon pipelines Details
You can also click on Tenders for more   
For reference purposes the website carries here the following Newsclips:  
8Oil prices stable as OPEC says market is rebalancing Details
8Environmental groups denounce Trump override of climate plan Details 
8CIL fuel supply to power plants rises by 21 per cent in September Details
8MNGL to increase piped gas network by 42,000 households Details
8Global oil CEOs seek reforms, promise big investments to PM Modi Details
8Natural gas trading exchange proposal to be sent to cabinet soon: Dharmendra Pradhan Details
8Crude Oil Prices Up In Asia As Market Looks To API Estimates Details
8India offers $300 billion investment chance in oil sector: Dharmendra Pradhan Details
8Trishna Gas project to be operational by Mar'19: ONGC Details
You can also click on Newsclips for more   
Details
8Project Name: Greenfield Hydroeletric Project
8Project Cost: Rs 900 crore
8Project Description: The owner carrying out the detailed project report activities for scoping the environment clearance for a 96 MW (2*48 MW) greenfield hydel project. TOR has been accorded on 15th October 2013 which would be valid for four years for S & I works, and after its expiry the proponent has to apply for fresh TOR. DPR has been submitted to CWC and CEA for appraisal. At present, survey & investigation works are in progress along with EIA studies which would take another 8-10 months for completion. NBWL clearance is also awaiting. The owner will come out with package wise contracts costing 258.79 crores as civil package and 168.30 crores as HM & EM packages.
8Project Event: RFQ for civil works are expected by Q4 of 2018.
8Expenditure Approval: Q2:2018
8RFQ Date: Q4:2018
8Release Date: Q1:2019
8Start Date: Q2:2019
8Completion Date: Q3:2023
Click here for more information
8Project Name: Greenfield Hydroeletric Project
8Project Cost: Rs 1600 Crores
8Project Description: The owner is planning to set up a 52 MW (2*26 MW) hydel plant. The  Hydroelectric Project obtained an extension on TOR in February, 2017 due to capacity revision from 80 MW to 52 MW. The DPR has been prepared and SIA (Social Impact Assessment) studies are being carried out at present. Earlier this year, the owner had floated an EOI, inviting private players to form a JV with it, for executing this project but no one has been selected yet. The company is expected to float RFQs for major hydro-mechanical equipment (i.e turbine-generator) in 2019.
8Project Event: RFQs for turbine-generator (T-G) is expected to be out in 2019.
8Expenditure Approval: 2015
8RFQ Date: 2019
8Release Date: 2019
8Start Date: 2019
8Completion Date: 2024
Click here for more information
Details
The website carries here a travel guide for the oil & gas traveler.
8This includes hotel pricing in oil & gas destinations, air travel advisories and best routes to take to destinations
8What are the latest travel trends in big oil and gas companies?
8Which are the latest hotspots?
8How do large oil & gas companies handle their travel portfolios?
Click on Reports for more Details
8Reliance Industries’ (RIL), strong refining margins will be somewhat offset by subdued polyester spreads. However ramp-up in new capacities and benefit of ethane imports will buoy earnings. Click on Report for more.
8Find out more on a young steel structural company trying to be bring in more orders from the oil & gas industry. click on Report for more.
8In the vessel demolition market Pakistan continues to lead in terms of bulk tonnage, with prices at region $400/ldt. Meantime, Bangladeshi and Indian prices remained stable at region $
380/ldt but with upward trends. Click on Report for more.
8Find out more on all reported tanker sales for the first week of October. Click on Report for more.
8Find out more on how Adani and Essar are diversifying up the value chain in the ports sector. Also more on the investment opportunities available today in the India ports. Click on Report for more.
8Find out more on major global oil & gas events in October, 2017. Click on Report for more.
8The pace of LNG supply growth and slowdown in global gas demand growth has raised the possibility that LNG will need to capture significant volumes from coal outside of ttraditional coal-to-gas switching markets to balance. Find out more. Click on Report for more.
8According to one well researched forecast made this week, sentiment headwinds will slow the recovery in crude prices and are the primary reason for a modest $1–2/bbl decrease to their earlier prediction on how prices are going to be until 2019. The latest projection is that the WTI price will average $50/bbl in 2017, $52/bbl in 2018, and $56/bbl in 2019. As for gas prices, the forecast is that Henry Hub natural gas prices will  average $3.06/MMBtu in 2017, $2.85 in 2018, and $3.00 in 2019. Find out more on the rationale behind these projections. Click on Report for more.
8Comprehensive monthly data on India oil & gas output, along with petroleum product output, imports and exports. Click on Report for more.
8Find out more on the growing oil & gas relationship between India and Angola. Click on Report for more. Details
8Project Name: Greenfield LPG Bottling Plant
8Project Cost: Rs 155 Crore
8Project Description: An existing company is planning to construct an LPG bottling plant with a capacity of 44 TMTPA.
8Project Event: RFQ for a Project Management Consultant is to be expected by February 2018.
8Expenditure Approval : Q2:2017
8RFQ Date : Feb/2018
8Release Date: Mar/2018
8Start Date : Q2:2018
8Completion Date : Q2:2020
Click here for more details.
8Project Name: Additional Tankage POL Terminal Project
8Project Cost: Rs 9 Crore
8Project Description: An existing company is planning to expand its capacity by constructing a new Ethanol tank with a capacity of 1600 KL. The capacity will then go up from 76017 KL to 77617 KL.
8Project Event: RFQ for Project Management Consultant is to be expected by December 2017.
8Expenditure Approval : Q2:2017
8RFQ Date : Dec/2017
8Release Date: Jan/2018
8Start Date : Q2:2018
8Completion Date : Q2:2019
Click here for more details.
8Project Name: Oilfield Development Drilling
8Project Cost: Rs 370 Crore
8Project Description: Promoter is planning the development drilling of oil wells in a Mining Lease Block.The project is listed out as an expansion project for the already existing 20 wells development drilling project. Currently, the well fluid collection and testing facilities for Tanot Field are located at existing GGS and GPC, each having a Gas processing capacity of 1 MMSCMD and 0.4 MMSCMD respectively. The rig package and pipeline contract are in the final stage of award.  RFQs for all well consumables and production equipment, namely X-Mas trees, Tubing Head Spools, Hanger Flanges / Tubing Hangers, Separators with all accessories, Steam Jacket, Ground X-Mas tree, Tubing Pipes for surface fittings and flare line etc. are expected shortly.
8Project Event: RFQ for hiring civil contractor for construction works is expected by end October 2017.
RFQ for equipment is expected by November 2017.
8Expenditure Approval: Q4/2016
8RFQ Date: Oct/2017
8Release Date: Nov/2017
8Start Date: Jun/2018
8Completion Date: Q2/2021
Click here for details
Details
The website carries here an interesting analysis on how the basic economic principles on which oil rich Gulf nations have operated so far are being turned upside down subsequent to the dramatic fall in oil prices.
8These countries have lived so far on the classic theory of rents, as rentier states, where citizens are spared taxes, and rents earned by the states are distributed to the citizens in various ways.
8The rentier state also allows a despotic regime to buy their citizens servitude.
8With oil prices remaining low, there will have to be a shift from the ‘cradle to grave’ welfare system to a different system where citizen and the private sector expected to bear the burden of adjustment.
8And these countries, lead by Saudi Arabia, are adjusting badly so far
Click on Reports for a compellingly new insight on the subject Details
If you want to know more about the global gas industry and the latest developments, what is it that you should be reading?
8The website provides links to 65 reports which will make you a gas sector expert.
8All of these are latest reports, dating only to 2017
Click on Reports for more Details
Find out more on an Indian oil and gas services company which claims to be among the largest such companies in the world
8It also claims to be the fast growing company in the world and why it thinks the future has more in store.
8And how 2016-17 was the inflection year for it.
8The website also carries here Q&A with the company.
Click on Reports for more Details
Find out more on the contrary view of the rig market from a rig supplier who has gone bullish by going on a jack up rig acquisition spree.
8It claims drilling activity will have to go up three fold to make up for the deficit that has been built up so far.
8Expected competitive jack-up fleet supply vs. potential demand projections are given here, showing high potential demand.
8There is already a 100% uptick in demand in 2017, the report says.
8What are the actual company-wise cash breakeven costs of jack-up rigs, as per latest projections
8The conclusion is that that there is a significant upside potential from investing at a cycle trough.
Click on Reports for more Details
The website carries here a global crude breakeven cost comparison.
8The data shows that more global supplies are capable of coming into the market at $ 50/bbl on less investment due to a vast increase in productivity.
8While market rebalancing is happening, it is now taking longer than previously thought.
8Also, get more insight on what is the analysts' view on oil prices remaining lower for longer. What is the new price band projected by analysts globally going into the future? Consensus views today are down sharply as against early 2017 and 2016 outlooks
8Find out what is the analyst range of how gas prices are going to behave going ahead, until the year 2025. What are the lower and upper limits?
Click on Reports for more Details
 Ammonia-Urea Energy Saving ProjectEquipment RFQs in January, 2018
8Cost - Rs 481 Crore
8Project Description: A Fertilizer company is planning to reduce the energy consumption of its Ammonia and Urea units from 8.73 Gcal/MT to 8.40 Gcal/MT and 6.75 Gcal/MT to 6.45 Gcal/MT respectively in India. The capacity of the ammonia plant is 1045 MTPD and the urea capacity is 1000 MTPD. The equipment requirements are 2 nos of GTG with a capacity 25 MW (ISO Rating), 2 nos of HRSG with a capacity 65 TPH, Replacement of turbine for the Benfield Solution Pump in Ammonia with new motor, De-aerator (2 nos.) with HP BFW Pump motor set 2 x (1+1), One PRDS system for 12 ata to 4.5 ata in the Ammonia plant, Modification in Power Distribution System.
8
Project Event: The selection process for the LSTK contractor is on and it is expected that the selected contractor will release equipment RFQs in January 2018.
Click here for more information
Super Phosphate-Sulphuric Acid & Granulated NPK Fertilizer Expansion Project 
8Cost - Rs 15 Crore
8Project Description: A Fertilizer company is planning is awaiting environmental clearance for its expansion of Super Phosphate Unit from 66000 TPA to 200000 TPA, Granulated NPK Fertilizer from 60000 TPA to 200000 TPA, Sulphuric acid from 33000 TPA to 50000 TPA in India. The equipment requirements are Crane, Hopper, Feeder, Conveyor, Valve, Grinding Mill, Tank, Separator, Pump, ID Fan, Collector, Generator Mixer, Den, Scrubber, Screen, Mill, Elevator, Drum, Furnace, Cyclone, Blower, Fan, Belt, Weighing machine, Steam Turbine Generators, Economizers, Reheaters, Boilers, Sulphur Combustor, Drying Towers, Absorbers, Absorber Exchangers, Sulphur filters, Sulphuric Melting Tank, motor, Pumps and more
8
Project Event: RFQ for a contractor is likely to be released in November or December in place of October 2017 due to a delay in environmental clearance
Click here for more information
 Ammonia-Urea Annual Shutdown Maintenance Project 
8Cost - Rs 40 Crore
8Project Description: A Fertilizer company is planning an annual shutdown maintenance in July or August 2018 at their existing fertilizer complex in India. The existing capacity is made up of 1520 MTPD of Ammonia, 2610 MTPD of Urea and 51 MW of Captive Power. Pre-Vendor Qualification is necessary for a maintenance contractor.
8
Project Event: Tender for a maintenance contractor is likely to be released in January 2018
Click here for more information   
Details
For reference purposes the website carries here the following tenders:
8Supply and Installation of Level Transmitters Details
8Terminal Works for Dhamra Angul Pipeline along with Spurlines to Paradip, Bhubaneswar and Cuttack under Jagdishpur-Haldia-Bokarodhamra Pipeline Project Details
8Procurement of Gas Chromatograph for Sulphur Analysis for Cauvery Basin Details
8Procurement of Calibration Gas Details
8Civil works at drill site BMDD in North Bank area Details
8Civil works at drill site DGAA_A & DGDG in Demualgaon area Details
8Conducting Digital Radiography of Insulated Piping for Profiling and Thickness Measurement Details
8Supply of Valves at refinery Details
You can also click on Tenders for more   
For reference purposes the website carries here the following Newsclips:  
8Opec sees 'extraordinary' steps needed for oil market stability Details
8Hydrogen is right choice as fuel for automobiles: Scientist G Madhavan Nair Details 
8Excise cut and mounting oil import bill, should the government be worried? Details
8Petrol pumps nationwide to be shut for 24 hrs from October 12 midnight Details
8India looks at strategic partnership with global oil producers Details
8PM Modi says status of energy sector in India highly uneven Details
8Cairn Oil and Gas to invest $4.6 billion in new exploration Details
8Top oil companies' heads for bringing oil under GST: Amitabh Kant Details
8India, Saudi Arabia must elevate ties to a much higher plane: Saudi Aramco CEO Details
8Oil CEOs seek reforms, promise big investments Details
You can also click on Newsclips for more   
Details
8Project Name: Brownfield LPG Bottling Plant
8Project Cost: Rs 143 Crore
8Project Description: An existing company is planning to expand its existing capacity from 11 TMTPA to 60 TMTPA in the LPG bottling plant.
8Project Event: RFQ for Project Management Consultant is expected by December 2017.
8Expenditure Approval : Q2:2017
8RFQ Date : Dec/2017
8Release Date: Jan/2018
8Start Date : Q1:2018
8Completion Date : Q1:2020
Click here for more details.
8Project Name: DG Set Hiring
8Project Description: Promoter is planning to hire 6 Diesel Generators (DG Sets) for various ongoing projects. The project involves supply as well as maintenance of Gensets on annual contract basis for an overall period of 3 years. The contractor shall be responsible for the supply of fuel. A pre-qualification criteria of minimum 2 years shall be put forward from promoter's end. Further RFQs for the project are expected shortly.
8Project Event: RFQ for hiring Diesel Gensets are expected by November 2017.
8Expenditure Approval: Sep/2017
8RFQ Date: Nov/2017
8Release Date: Dec/2017
8Start Date: Feb/2018
8Completion Date: Feb/2021