Rs 700 crore LPG import terminal: An update
Dec 27: A Rs 700 crore all-round upgradation of a LPG import terminal is coming up
8TOR is expected to be granted in Q-1, 2017
8EIA consultant has already been hired
Various proposed facilities considered for capacity augmentation can be classified as:
1)Process equipments which includes

a) Jetty Import facilities
b) Propane/Butane /LPG storage, handling & dispatch facilities
c) Flash Gas Compressor Section
2) Offsite & Utilities which includes
a) Steam generation
b) Instrument Air system
c) Cooling Water system
d) HSD storage and transportation
3) Electrical system & equipments including
a) New Switchyard, pole structure, panel etc.
b) New Transformer
c) New switchboard,
d) New PMCC
e) New HT/LT DG sets,
f) Lighting & Earthing for proposed facilities
4) Control & Instrumentation with latest supporting Hardware.